433 W 107TH ST 90003
Certificate Information: 433 W 107TH ST 90003
- Application / Permit
- 21010-10000-06291
- Plan Check / Job No.
- B21LA22719
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW GARAGE WITH NEW ADU ON TOP, PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/12/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/11/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/20/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| Applicant returned to address corrections | 4/6/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/8/2022 | MAHNAZ NOURHASHEMI |
| Issued | 4/12/2022 | APPLICANT |
| CofO in Progress | 2/6/2023 | JAMES CHAVEZ |
| Permit Finaled | 2/7/2023 | ANSON MAGLASANG |
| CofO Issued | 2/7/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/7/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2022 | CHRISTOPHER ROCHA |
| Permit | Cleared | 2/2/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 3/11/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 3/11/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/14/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/31/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Total Property Services; Lic. No.: 732965-B | 712 E MANCHESTER BLVD INGLEWOOD, CA 90301 |
| Engineer | Cala,, Kyle; Lic. No.: C86671 | 5900 MURIETTA AVE 102 VAN NUYS, CA 91401 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/26/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 8/26/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 9/1/2022 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/1/2022 | Partial Approval | ANSON MAGLASANG |
| Sewer | 9/1/2022 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/14/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 10/7/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 10/20/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Gas Test | 10/27/2022 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 10/27/2022 | Approved | JOHN KLARIN |
| Wood Frame | 10/27/2022 | Approved | JOHN KLARIN |
| Insulation | 11/3/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/8/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 11/8/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/8/2022 | Approved | JOHN KLARIN |
| Gas Test | 12/13/2022 | Approved | JAMES CHAVEZ |
| Sewer | 12/13/2022 | Approved | JAMES CHAVEZ |
| Underground Mechanical | 12/13/2022 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 1/12/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 1/12/2023 | Approved | JAMES CHAVEZ |
| Final | 1/12/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 1/12/2023 | Approved | JAMES CHAVEZ |
| HVAC-Final | 1/12/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Final | 1/12/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 1/12/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 1/12/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Service/Power Release | 1/12/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 1/12/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 1/12/2023 | Approved | JAMES CHAVEZ |
| Final | 1/18/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Final | 1/18/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 1/18/2023 | Approved | JAMES CHAVEZ |
| Final | 2/6/2023 | OK to Issue CofO | JAMES CHAVEZ |