1131 E 118TH DR 90059
Certificate Information: 1131 E 118TH DR 90059
- Application / Permit
- 21010-10000-06279
- Plan Check / Job No.
- B21LA22638
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of 367 sq ft garage to a two story 1156 sq ft Accessory dwelling unit
- Permit Issued
- Issued on 2/22/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | JAD BASMA |
| Corrections Issued | 2/17/2022 | JAD BASMA |
| Quality Review Completed | 2/23/2022 | KEN GILL |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Plan Check Approved | 12/21/2022 | JAD BASMA |
| Plan Check Approved | 12/21/2022 | JAD BASMA |
| Issued | 2/22/2023 | APPLICANT |
| CofO in Progress | 6/14/2025 | ANTHONY EGSON |
| CofO Issued | 6/16/2025 | ANSON MAGLASANG |
| Permit Finaled | 6/16/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2022 | JEANETTE VONG |
| Address approval | Cleared | 6/10/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 10/31/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 11/21/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2022 | JEANIE LAM |
| Sewer availability | Cleared | 11/28/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 12/1/2022 | TORI CHEN |
| Hold | Cleared | 3/29/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | A & A Construction; Lic. No.: 668812-B | 1944 W 152ND STREET GARDENA, CA 90249 |
| Engineer | Ec+Asso, Engineering; Lic. No.: C77737 | 1412 ESPANOL AVE MONTEBELLO, 90640 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/25/2023 | Corrections Issued | JOHN KLARIN |
| Sewer | 5/25/2023 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 5/31/2023 | Approved | JOHN KLARIN |
| Sewer | 5/31/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/17/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 7/17/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 7/17/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/17/2023 | Approved | JOHN KLARIN |
| MERV13>=Rough | 7/17/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/17/2023 | Approved | JOHN KLARIN |
| Sewer | 7/17/2023 | Approved | JOHN KLARIN |
| Insulation | 8/4/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/4/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/29/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/29/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 1/10/2024 | Partial Approval | JOHN KLARIN |
| PLUMBING-Rough | 1/10/2024 | Partial Approval | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Not Ready | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| ELECTRICAL-Rough | 2/13/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 2/16/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 4/4/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 4/4/2024 | Partial Inspection | ANSON MAGLASANG |
| ELECTRICAL-Final | 5/14/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 8/22/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 8/22/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 8/22/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 8/22/2024 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 8/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 8/22/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 8/22/2024 | Partial Inspection | BARRY HACHE |
| ELECTRICAL-Final | 11/15/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 11/15/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 11/15/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 11/15/2024 | Corrections Issued | ANTHONY EGSON |
| MERV13>=Final | 11/15/2024 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 11/15/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 2/27/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 2/27/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Final | 2/27/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 2/27/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 5/12/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 5/12/2025 | Partial Approval | ANTHONY EGSON |
| MERV13>=Final | 5/12/2025 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 5/12/2025 | Approved | ANTHONY EGSON |
| Special/Order Compliance | 6/11/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 6/13/2025 | Approved | ANTHONY EGSON |
| Final | 6/13/2025 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 6/13/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 6/13/2025 | Approved | ANTHONY EGSON |
| MERV13>=Final | 6/13/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/13/2025 | Approved | ANTHONY EGSON |