6941 N SIMPSON AVE 1-2 91605

Certificate Information: 6941 N SIMPSON AVE 1-2 91605

Application / Permit
21010-10000-06267
Plan Check / Job No.
B21LA22592
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED 2 CAR GARAGE (REAR BLDG)
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
239433 - CofO Issued More Information
239433 - CofO Issued More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 KHEDER ALRAZAA
Corrections Issued 12/22/2021 KHEDER ALRAZAA
Quality Review Completed 12/30/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/12/2022 APPLICANT
Applicant returned to address corrections 2/11/2022 KHEDER ALRAZAA
Applicant returned to address corrections 2/24/2022 KHEDER ALRAZAA
Plan Check Approved 5/20/2022 KHEDER ALRAZAA
Issued 6/16/2022 APPLICANT
CofO in Progress 11/8/2023 ROBERT GOLD
Permit Finaled 11/14/2023 RUBEN SALAS
CofO Issued 11/14/2023 RUBEN SALAS
Permit Finaled 11/14/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/27/2021 CARLOS AGUILERA
Highway dedication Cleared 12/27/2021 CARLOS AGUILERA
Permit Cleared 12/27/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/6/2022 CARLOS AGUILERA
Sewer availability Cleared 1/6/2022 CARLOS AGUILERA
Trees in Parkway Cleared 2/18/2022 ADALBERTO VERA
Low Impact Development Cleared 2/22/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/22/2022 CARLOS AGUILERA
Frnt yard landscape/Water mgmt Cleared 3/3/2022 LAUREN PADICK
Construction near power lines Cleared 3/9/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 3/11/2022 MATTHEW CRAIG

Contact Information

Contractor Inhance Construction Inc; Lic. No.: 1073871-B 7257 BEVERLY RD STE 205      LOS ANGELES, CA 90036
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2022 Partial Approval JOHN HAYES
Underground Mechanical 10/21/2022 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 11/2/2022 Partial Approval JOHN HAYES
Footing/Foundation/Slab 11/15/2022 Approved JOHN HAYES
Deputy Wood Construction 12/12/2022 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Approval JOHN HAYES
Deputy Wood Construction 1/19/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Partial Approval JOHN HAYES
Gas Test 2/23/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 2/23/2023 Partial Approval JENNIFER RABUCHIN
Deputy Wood Construction 3/20/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Partial Approval MISAEL ESPARZA
Shower Pan 3/23/2023 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 3/30/2023 Not Ready for Inspection JOHN HAYES
Shower Pan 3/30/2023 Corrections Issued JOHN HAYES
Deputy Drilled-In Anchors 4/19/2023 Conditional Approval JOHN HAYES
Deputy Reinf. Concrete 4/19/2023 Conditional Approval JOHN HAYES
Shower Pan 4/20/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/4/2023 Approved JOHN HAYES
HVAC-Rough 5/4/2023 Approved JOHN HAYES
PLUMBING-Rough 5/4/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 5/15/2023 Corrections Issued JOHN HAYES
Green Building Rough 5/15/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 5/15/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 5/15/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/23/2023 Approved ROBERT GOLD
Green Building Rough 5/23/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 5/23/2023 Not Ready for Inspection ROBERT GOLD
Special/Order Compliance 5/23/2023 Approved ROBERT GOLD
Verify Sprinkler Sign Off 5/23/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 5/30/2023 Partial Approval JOHN HAYES
Insulation 6/5/2023 Approved JOHN HAYES
Drywall Nailing 6/14/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/14/2023 Partial Approval JACK KARGODORIAN
Sewer 7/27/2023 Approved JUAN VALENZUELA
Underground Mechanical 7/27/2023 Approved JUAN VALENZUELA
Final 10/2/2023 Corrections Issued JOHN HAYES
Gas Test 10/2/2023 Approved JOHN HAYES
HVAC-Final 10/2/2023 Approved JOHN HAYES
PLUMBING-Final 10/2/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 10/3/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/3/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 10/10/2023 Partial Approval JOHN HAYES
Service/Power Release 10/10/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 10/10/2023 Partial Approval JOHN HAYES
Final 10/26/2023 Partial Inspection ROBERT GOLD
Green Building Final 10/26/2023 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Approved ROBERT GOLD
Service/Power Release 10/26/2023 Conditional Approval ROBERT GOLD
Smoke Detectors 10/26/2023 Approved ROBERT GOLD
Final 11/8/2023 OK to Issue CofO ROBERT GOLD
Service/Power Release 11/8/2023 Approved ROBERT GOLD