162-162 1/2 N ALEXANDRIA AVE 90004

Certificate Information: 162-162 1/2 N ALEXANDRIA AVE 90004

Application / Permit
21010-10000-06260
Plan Check / Job No.
B21LA22586
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED GARAGE & RECREATION ROOM AT FIRST FLOOR. FRONT ON LOT W APN 5518012030 1 OF 4
Permit Issued
Issued on 4/29/2024
Issuing Office
Current Status
CofO Issued on 12/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 SERGIO GUTIERREZ
Corrections Issued 12/21/2021 SERGIO GUTIERREZ
Quality Review Completed 12/22/2021 FARUK SEZER
Building Plans Picked Up 3/16/2022 APPLICANT
Applicant returned to address corrections 9/22/2022 SERGIO GUTIERREZ
Plan Check Approved 12/27/2023 SERGIO GUTIERREZ
Issued 4/29/2024 APPLICANT
CofO in Progress 12/10/2025 WILLIAM SIERRA
Permit Finaled 12/13/2025 DEROLD HAUFF
CofO Issued 12/13/2025 DEROLD HAUFF
Permit Finaled 12/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/14/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/14/2022 CELINA MORENO
Highway dedication Cleared 1/14/2022 CELINA MORENO
Permit Cleared 1/14/2022 CELINA MORENO
Sewer availability Cleared 1/26/2022 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 3/3/2022 RICHARD REASER
Opn space landscape/Water mgmt Cleared 3/3/2022 RICHARD REASER
Hydrant and Access approval Cleared 3/11/2022 MATTHEW CRAIG
Flood clearance Cleared 10/31/2022 SAMSON WONG
Low Impact Development Cleared 12/9/2022 TA ANH
Roof/Waste drainage to street Cleared 2/2/2023 THAN WIN
Flood clearance Cleared 12/6/2023 MIGUEL RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/3/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/12/2024 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 7/15/2024 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 7/15/2024 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 7/15/2024 Corrections Issued JOSEPH MCGARRY
FLOOD-Elevation Certificate 7/22/2024 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Partial Approval WILLIAM SIERRA
PLUMBING-Rough 11/7/2024 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved WILLIAM SIERRA
HVAC-Rough 11/12/2024 Approved WILLIAM SIERRA
Special/Order Compliance 11/12/2024 Corrections Issued WILLIAM SIERRA
Shower Pan 11/22/2024 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 12/2/2024 Not Ready for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 12/2/2024 Not Ready for Inspection JOHN QUINTANILLA
Special/Order Compliance 12/3/2024 Approved WILLIAM SIERRA
ELECTRICAL-Rough 12/5/2024 Partial Approval WILLIAM SIERRA
Interior/Exterior Lathing 12/5/2024 Partial Approval WILLIAM SIERRA
BUILDING-Rough-Frame 12/6/2024 Partial Approval WILLIAM SIERRA
Shower Pan 12/6/2024 Corrections Issued WILLIAM SIERRA
Insulation 12/10/2024 Approved WILLIAM SIERRA
Interior/Exterior Lathing 12/10/2024 Not Ready for Inspection WILLIAM SIERRA
Shower Pan 12/10/2024 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 12/13/2024 Approved WILLIAM SIERRA
Drywall Nailing 12/13/2024 Partial Inspection WILLIAM SIERRA
FLOOD-Proofing Certificate 12/13/2024 Approved WILLIAM SIERRA
Green Building Rough 12/13/2024 Approved WILLIAM SIERRA
Interior/Exterior Lathing 12/13/2024 Approved WILLIAM SIERRA
METHANE-Rough 12/13/2024 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 12/13/2024 Approved WILLIAM SIERRA
Drywall Nailing 12/24/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 4/2/2025 Partial Approval WILLIAM SIERRA
Gas Test 4/24/2025 Approved WILLIAM SIERRA
Underground Mechanical 4/24/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 9/18/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 9/18/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 9/18/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Final 10/27/2025 Approved FREDDIE RIVERA
HVAC-Final 10/27/2025 Approved FREDDIE RIVERA
PLUMBING-Final 10/27/2025 Approved FREDDIE RIVERA
FLOOD-Elevation Certificate 12/9/2025 Approved WILLIAM SIERRA
Final 12/9/2025 OK to Issue CofO WILLIAM SIERRA
Footing/Foundation/Slab 12/9/2025 Approved WILLIAM SIERRA
Green Building Final 12/9/2025 Approved WILLIAM SIERRA
METHANE-Barrier 12/9/2025 Approved WILLIAM SIERRA
METHANE-Subgrade 12/9/2025 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved WILLIAM SIERRA
Service/Power Release 12/9/2025 Approved WILLIAM SIERRA
Smoke Detectors 12/9/2025 Approved WILLIAM SIERRA