5152 1/2-1/4 E ITHACA AVE 90032
Certificate Information: 5152 1/2-1/4 E ITHACA AVE 90032
- Application / Permit
- 21010-10000-06253
- Plan Check / Job No.
- B21LA22581
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED TWO ADUs PER STATE LAW PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 7/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | KHUONG TRUONG |
| Corrections Issued | 12/22/2021 | KHUONG TRUONG |
| Quality Review Completed | 12/30/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/12/2022 | APPLICANT |
| Plan Check Approved | 6/23/2023 | MAHNAZ NOURHASHEMI |
| No Progress | 6/23/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/30/2023 | MAHNAZ NOURHASHEMI |
| Issued | 7/5/2023 | APPLICANT |
| CofO in Progress | 6/12/2024 | LILIANA PORTILLO |
| Permit Finaled | 6/14/2024 | DEROLD HAUFF |
| CofO Issued | 6/14/2024 | DEROLD HAUFF |
| Permit Finaled | 6/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2021 | CELINA MORENO |
| Sewer availability | Cleared | 12/29/2021 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 3/30/2023 | ISMAEL HERNANDEZ |
| "D" conditions | Cleared | 4/14/2023 | JASON CHAN |
| "Q" conditions | Cleared | 4/14/2023 | JASON CHAN |
| ZI | Cleared | 4/14/2023 | JASON CHAN |
| Miscellaneous | Cleared | 5/12/2023 | JASON CHAN |
| Low Impact Development | Cleared | 5/22/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/22/2023 | WALLIE JONG |
| GPI Written Notices | Cleared | 6/23/2023 | KHUONG TRUONG |
| Grading Pre-Inspection | Cleared | 6/23/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2023 | Partial Inspection | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 8/31/2023 | Partial Inspection | AMY COLIN |
| PLUMBING-Rough | 8/31/2023 | Partial Approval | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Approved | AMY COLIN |
| Deputy Reinf. Concrete | 9/15/2023 | Conditional Approval | AMY COLIN |
| Deputy Wood Construction | 9/28/2023 | Conditional Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 10/27/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 11/9/2023 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 11/9/2023 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/19/2023 | Corrections Issued | AMY COLIN |
| Deputy Wood Construction | 12/19/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 12/19/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 12/19/2023 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 12/19/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 12/19/2023 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 1/12/2024 | Partial Approval | AMY COLIN |
| Shower Pan | 1/12/2024 | Approved | AMY COLIN |
| Insulation | 1/18/2024 | Approved | AMY COLIN |
| Drywall Nailing | 1/22/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/22/2024 | Approved | BRENDAN MORELLI |
| Gas Test | 3/7/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 3/7/2024 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 3/7/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 3/26/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 4/2/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/25/2024 | Approved | LILIANA PORTILLO |
| Final | 4/25/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/25/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 4/25/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 4/25/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 4/25/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 4/25/2024 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 4/25/2024 | Approved | LILIANA PORTILLO |
| Final | 5/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 5/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 6/10/2024 | Approved | LILIANA PORTILLO |
| Final | 6/10/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 6/10/2024 | Approved | LILIANA PORTILLO |