13106 W PONTOON PL 90049

Certificate Information: 13106 W PONTOON PL 90049

Application / Permit
21010-10000-06244
Plan Check / Job No.
B21LA22514
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 JAD BASMA
Corrections Issued 12/23/2021 JAD BASMA
Quality Review Completed 12/28/2021 MICHAEL PEREZ
Applicant returned to address corrections 2/25/2022 JAD BASMA
Building Plans Picked Up 4/1/2022 APPLICANT
Plan Check Approved 5/27/2022 JAD BASMA
Issued 5/31/2022 APPLICANT
CofO in Progress 7/14/2023 OGANES TARAKHCHYAN
Permit Finaled 7/19/2023 DANIEL ORRANTE
CofO Issued 7/19/2023 DANIEL ORRANTE
Permit Finaled 7/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 2/25/2022 STEVEN JIN
Hydrant and Access approval Cleared 4/2/2022 DWIGHT SANKEY
Eng Process Fee Ord 176,300 Cleared 4/8/2022 DINAH GARIN
Sewer availability Cleared 4/8/2022 DINAH GARIN
Grading Pre-Inspection Cleared 4/29/2022 KIRK LINKLATER
Low Impact Development Cleared 5/3/2022 NICK RAYGOZA
Trees in Parkway Cleared 5/6/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 5/12/2022 DINAH GARIN
GPI Written Notices Cleared 5/31/2022 MICHAEL PEREZ

Contact Information

Contractor Perfect Project Llc; Lic. No.: 1002945-B 2611 BRIGHTON AVENUE      LOS ANGELES, CA 90018

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/19/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 8/23/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 8/26/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/30/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 9/1/2022 Partial Approval KEVIN SARGSYAN
Sewer 9/6/2022 Approved KEVIN SARGSYAN
Deputy Reinf. Concrete 9/7/2022 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 9/16/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 9/16/2022 Approved KEVIN SARGSYAN
Underground Mechanical 10/5/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 10/6/2022 No Access for Inspection KEVIN SARGSYAN
Gas Test 10/18/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 10/18/2022 Partial Approval KEVIN SARGSYAN
Gas Test 10/20/2022 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 11/4/2022 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 12/12/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 2/6/2023 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 2/6/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/6/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/7/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/8/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 2/23/2023 Not Ready for Inspection HERBERT GIRON
Shower Pan 2/23/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 2/24/2023 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/28/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 2/28/2023 Approved OGANES TARAKHCHYAN
Wood Frame 3/6/2023 Approved OGANES TARAKHCHYAN
Insulation 3/13/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 3/28/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/6/2023 Approved STEPHANIE SWANSON
Grading Pre-Inspection 5/24/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 6/7/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 6/7/2023 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Final 6/14/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 7/3/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 7/3/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Final 7/3/2023 Approved OGANES TARAKHCHYAN
Service/Power Release 7/3/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/5/2023 Approved OGANES TARAKHCHYAN
Final 7/5/2023 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 7/5/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 7/5/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 7/5/2023 Approved OGANES TARAKHCHYAN
Smoke Detectors 7/5/2023 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 7/5/2023 Approved OGANES TARAKHCHYAN
Final 7/13/2023 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved OGANES TARAKHCHYAN