238 1/4 E 51ST ST 90011

Certificate Information: 238 1/4 E 51ST ST 90011

Application / Permit
21010-10000-06233
Plan Check / Job No.
B21LA22467
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ADU #2 (Two ADUs per State Law, CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
Permit Issued
Issued on 9/28/2023
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 RAHEL BEYENE
Corrections Issued 12/3/2021 RAHEL BEYENE
Building Plans Picked Up 12/7/2021 APPLICANT
Applicant returned to address corrections 8/14/2023 MINA HABILI
Plan Check Approved 9/19/2023 MINA HABILI
Issued 9/28/2023 APPLICANT
CofO in Progress 2/24/2026 ALEJANDRO DE ARTOLA
CofO Issued 2/26/2026 DEROLD HAUFF
Permit Finaled 2/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/8/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/13/2021 WALLIE JONG
Sewer availability Cleared 12/13/2021 WALLIE JONG
Hydrant and Access approval Cleared 2/23/2022 JOHN CONNEALLY
Low Impact Development Cleared 6/16/2023 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/18/2023 CHRISTINA BRACO

Contact Information

Contractor Jarh Builders Corporation; Lic. No.: 1074687-B 15740 PARAMOUNT BLVD #E      PARAMOUNT, CA 90723
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 5/6/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/6/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/20/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 5/21/2024 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 5/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 6/5/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/18/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 6/18/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/5/2024 Corrections Issued JUSTIN HAWLEY
HVAC-Rough 7/5/2024 Approved JUSTIN HAWLEY
Deputy Wood Construction 7/8/2024 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/11/2024 Conditional Approval MICHAEL LEWIS
Insulation 7/11/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 7/11/2024 Partial Approval MICHAEL LEWIS
Drywall Nailing 7/25/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 7/25/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/25/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 8/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 8/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 10/9/2025 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 10/9/2025 Approved MICHAEL LEWIS
ELECTRICAL-Final 1/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 1/20/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 1/20/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/24/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/24/2026 Approved ALEJANDRO DE ARTOLA
Final 2/24/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 2/24/2026 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 2/24/2026 Approved ALEJANDRO DE ARTOLA