2640-2640 1/2 E ROSEVIEW AVE 90065

Certificate Information: 2640-2640 1/2 E ROSEVIEW AVE 90065

Application / Permit
21010-10000-06193
Plan Check / Job No.
B21LA22316
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF SINGEL FAMILY DWELLING UNIT INTO AN ACCESSORY DWELLING UNIT (525 sq ft) PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/22/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/30/2021 MONICA RAMIREZ
Corrections Issued 12/1/2021 MONICA RAMIREZ
Applicant returned to address corrections 2/2/2022 MONICA RAMIREZ
Applicant returned to address corrections 3/8/2022 MONICA RAMIREZ
Plan Check Approved 3/19/2022 JOE VO
Plan Check Approved 3/22/2022 MONICA RAMIREZ
Issued 3/22/2022 APPLICANT
CofO in Progress 1/17/2023 OSVALDO PARAMO
CofO in Progress 1/17/2023 OSVALDO PARAMO
Permit Finaled 1/19/2023 DEROLD HAUFF
CofO Issued 1/19/2023 DEROLD HAUFF
Permit Finaled 1/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/22/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/29/2021 AMAAN MALIK
Sewer availability Cleared 3/8/2022 AMAAN MALIK
Supp. Use District POD/CDO/TDO Cleared 3/11/2022 NASHYA JENSEN

Contact Information

Contractor Diditan Group Inc; Lic. No.: 1008348-B       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/11/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 4/11/2022 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 4/11/2022 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 7/18/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 7/18/2022 Corrections Issued SCOTT FINNILA
Deputy Drilled-In Anchors 8/2/2022 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 8/15/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 8/29/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 8/29/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 8/29/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/2/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 9/2/2022 Approved OSVALDO PARAMO
Insulation 9/2/2022 Approved OSVALDO PARAMO
Drywall Nailing 9/19/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/19/2022 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 9/22/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/26/2022 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 9/30/2022 Approved OSVALDO PARAMO
Final 12/1/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/1/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 12/1/2022 Not Ready for Inspection OSVALDO PARAMO
Final 12/7/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 12/7/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 12/14/2022 Approved OSVALDO PARAMO
Final 12/14/2022 Corrections Issued OSVALDO PARAMO
Final 1/6/2023 Partial Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 1/6/2023 Approved ALIZAH MAYAGOITIA
Final 1/9/2023 OK to Issue CofO OSVALDO PARAMO