2640-2640 1/2 E ROSEVIEW AVE 90065
Certificate Information: 2640-2640 1/2 E ROSEVIEW AVE 90065
- Application / Permit
- 21010-10000-06193
- Plan Check / Job No.
- B21LA22316
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF SINGEL FAMILY DWELLING UNIT INTO AN ACCESSORY DWELLING UNIT (525 sq ft) PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2021 | MONICA RAMIREZ |
| Corrections Issued | 12/1/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/2/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/8/2022 | MONICA RAMIREZ |
| Plan Check Approved | 3/19/2022 | JOE VO |
| Plan Check Approved | 3/22/2022 | MONICA RAMIREZ |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 1/17/2023 | OSVALDO PARAMO |
| CofO in Progress | 1/17/2023 | OSVALDO PARAMO |
| Permit Finaled | 1/19/2023 | DEROLD HAUFF |
| CofO Issued | 1/19/2023 | DEROLD HAUFF |
| Permit Finaled | 1/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2021 | AMAAN MALIK |
| Sewer availability | Cleared | 3/8/2022 | AMAAN MALIK |
| Supp. Use District POD/CDO/TDO | Cleared | 3/11/2022 | NASHYA JENSEN |
Contact Information
| Contractor | Diditan Group Inc; Lic. No.: 1008348-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/11/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 4/11/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 4/11/2022 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/18/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 7/18/2022 | Corrections Issued | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 8/2/2022 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/15/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/29/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/29/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 8/29/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/2/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/2/2022 | Approved | OSVALDO PARAMO |
| Insulation | 9/2/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 9/19/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 9/22/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/26/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/30/2022 | Approved | OSVALDO PARAMO |
| Final | 12/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 12/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 12/7/2022 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 12/7/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 12/14/2022 | Approved | OSVALDO PARAMO |
| Final | 12/14/2022 | Corrections Issued | OSVALDO PARAMO |
| Final | 1/6/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/9/2023 | OK to Issue CofO | OSVALDO PARAMO |