865 N NAPOLI DR 90272

Certificate Information: 865 N NAPOLI DR 90272

Application / Permit
21010-10000-06178
Plan Check / Job No.
B21LA22279
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE NFPA-13D Require. 1 OF 5
Permit Issued
Issued on 7/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 ZAW HAN
Corrections Issued 12/21/2021 ZAW HAN
Quality Review Completed 12/22/2021 KEN GILL
Applicant returned to address corrections 3/8/2022 ZAW HAN
Building Plans Picked Up 3/14/2022 APPLICANT
Applicant returned to address corrections 4/14/2022 ZAW HAN
Applicant returned to address corrections 6/22/2022 ZAW HAN
Applicant returned to address corrections 6/27/2022 ZAW HAN
Applicant returned to address corrections 6/29/2022 ZAW HAN
Plan Check Approved 7/7/2022 ZAW HAN
Issued 7/8/2022 APPLICANT
CofO in Progress 3/27/2025 HERBERT GIRON
Permit Finaled 3/28/2025 RICHARD STEINBACH
CofO Issued 3/28/2025 RICHARD STEINBACH
Permit Finaled 3/28/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/17/2022 JOSE RODRIGUEZ
BHO/Hillside ordinance Cleared 1/21/2022 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 1/21/2022 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 1/21/2022 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 1/21/2022 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 1/21/2022 RAYMOND MUGAMBWA
Address approval Cleared 1/25/2022 ANTHONY MAINEZ
Permit Cleared 1/25/2022 ANTHONY MAINEZ
Sewer availability Cleared 1/26/2022 ANTHONY MAINEZ
Frnt yard landscape/Water mgmt Cleared 3/2/2022 MAXFIELD VERMY
Landscape for retaining wall Cleared 3/2/2022 MAXFIELD VERMY
Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN
Building over 36-ft Cleared 4/20/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/20/2022 CALOSHA APPROVED
Low Impact Development Cleared 4/21/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/25/2022 ANTHONY MAINEZ
Disturb/Remove Protected Trees Cleared 6/1/2022 ADALBERTO VERA
Trees in Parkway Cleared 6/1/2022 ADALBERTO VERA
GPI Written Notices Cleared 6/29/2022 KIRK LINKLATER
Grading Pre-Inspection Cleared 6/29/2022 KIRK LINKLATER
Green Code Cleared 6/29/2022 ZAW HAN
Haul Route Cleared 6/29/2022 VERONICA LOPEZ

Contact Information

Contractor Gibson Gordon Construction; Lic. No.: 524012-B 3000 31ST STREET SUITE G      SANTA MONICA, CA 90405
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301
Engineer Schmahl,, Lawrence Joseph; Lic. No.: L5748 11209 HOWARD STREET      WHITTIER, CA 90606
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 7/12/2022 Approved MICHAEL PELHAM
Deputy Grading 7/13/2022 Approved MICHAEL PELHAM
Deputy Grading 7/14/2022 Partial Approval JOHN KIDWELL
Deputy Grading 7/15/2022 Partial Approval JOHN KIDWELL
Pre-Inspection 8/3/2022 Approved ANDREW NAVE
Pre-Inspection 8/22/2022 Partial Inspection KEVIN SARGSYAN
Deputy Other (see comments) 8/30/2022 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 9/27/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 10/6/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 10/17/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 10/20/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 10/25/2022 Partial Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 10/27/2022 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 10/28/2022 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 10/28/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 12/6/2022 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 12/8/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 12/13/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 2/7/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/10/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/28/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 3/8/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 3/8/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 3/9/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 4/12/2023 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/13/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/17/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/21/2023 Partial Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval OGANES TARAKHCHYAN
Wood Frame 6/22/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 7/10/2023 Partial Approval OGANES TARAKHCHYAN
Structural Steel Frame 7/10/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/2/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 9/13/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 9/28/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/13/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/24/2023 Partial Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 10/27/2023 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/27/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 10/30/2023 Partial Approval OGANES TARAKHCHYAN
Wood Frame 11/3/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/6/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 11/9/2023 Conditional Approval ARAM AVEDISIAN
Green Building Rough 11/9/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/9/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 11/9/2023 Approved ARAM AVEDISIAN
Special/Order Compliance 11/9/2023 Corrections Issued ARAM AVEDISIAN
Verify Sprinkler Sign Off 11/9/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 11/13/2023 Partial Approval ARAM AVEDISIAN
Insulation 11/13/2023 Partial Approval ARAM AVEDISIAN
Drywall Nailing 11/21/2023 Partial Approval ARAM AVEDISIAN
HVAC-Rough 11/28/2023 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 11/28/2023 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 12/4/2023 Partial Approval ARAM AVEDISIAN
Insulation 12/20/2023 Not Ready for Inspection ARAM AVEDISIAN
Insulation 12/26/2023 Partial Approval KEVIN SARGSYAN
HVAC-Rough 1/11/2024 Not Ready for Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 1/18/2024 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 1/24/2024 Approved ARAM AVEDISIAN
HVAC-Rough 1/24/2024 Approved ARAM AVEDISIAN
Drywall Nailing 1/29/2024 Not Ready for Inspection MEL KHACHATOURIAN
Pre-Inspection 1/30/2024 Partial Inspection ARAM AVEDISIAN
Drywall Nailing 2/2/2024 Approved ARAM AVEDISIAN
Sewer 3/20/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 6/27/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 9/10/2024 Approved JESUS RODRIGUEZ
Service/Power Release 9/10/2024 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 10/9/2024 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 10/15/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/30/2024 Approved JESUS RODRIGUEZ
Service/Power Release 11/20/2024 Approved KENNETH NAGLE
PLUMBING-Final 12/10/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Ready EVAN COOPER
ELECTRICAL-Final 2/3/2025 Approved JESUS RODRIGUEZ
HVAC-Final 2/7/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Final 2/24/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/28/2025 Approved JESUS RODRIGUEZ
Final 2/28/2025 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 2/28/2025 Approved JESUS RODRIGUEZ
Green Building Final 2/28/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 2/28/2025 Approved JESUS RODRIGUEZ
Final 3/26/2025 OK to Issue CofO HERBERT GIRON
Reinforced Concrete Frame 3/26/2025 Approved HERBERT GIRON
Smoke Detectors 3/26/2025 Approved HERBERT GIRON