237 S AVENUE 58 90042

Certificate Information: 237 S AVENUE 58 90042

Application / Permit
21010-10000-06169
Plan Check / Job No.
B21LA22264
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. (N) 35 X 37' ADU per Ordinance 186481 “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 7/11/2022
Issuing Office
Current Status
CofO Issued on 5/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/30/2021 HERNAN ARREOLA
Corrections Issued 11/30/2021 HERNAN ARREOLA
Plan Check Approved 4/15/2022 HERNAN ARREOLA
Issued 7/11/2022 APPLICANT
CofO in Progress 5/23/2024 LILIANA PORTILLO
Permit Finaled 5/30/2024 DEROLD HAUFF
CofO Issued 5/30/2024 DEROLD HAUFF
Permit Finaled 5/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/22/2021 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 12/27/2021 ABEL CASILLAS
Grading Pre-Inspection Cleared 12/27/2021 SERGIO VALENZUELA
Sewer availability Cleared 12/27/2021 ABEL CASILLAS
GPI Written Notices Cleared 2/16/2022 HERNAN ARREOLA
HPOZ Cleared 3/21/2022 KATIE DEBIASE
Roof/Waste drainage to street Cleared 3/24/2022 AMAAN MALIK

Contact Information

Architect Van, Leer, Louisa B; Lic. No.: NA28646       ,
Contractor Innovative Renovations Inc; Lic. No.: 542716-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/8/2022 Not Ready for Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 9/14/2022 Approved AMY COLIN
PLUMBING-Rough 9/14/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved AMY COLIN
ELECTRICAL-Rough 2/8/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 2/8/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 2/28/2023 Approved AMY COLIN
Interior/Exterior Lathing 2/28/2023 Partial Approval AMY COLIN
Drywall Nailing 4/10/2023 Approved AMY COLIN
Green Building Rough 4/10/2023 Approved AMY COLIN
Sewer 5/18/2023 Corrections Issued AMY COLIN
Sewer 5/25/2023 Approved AMY COLIN
Shower Pan 5/25/2023 Approved AMY COLIN
Underground Mechanical 5/25/2023 Partial Approval AMY COLIN
Interior/Exterior Lathing 5/30/2023 Approved AMY COLIN
Footing/Foundation/Slab 6/13/2023 Approved AMY COLIN
Underground Mechanical 6/22/2023 Approved AMY COLIN
BUILDING-Rough-Frame 4/4/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/4/2024 Corrections Issued CRAIG VAUGHAN
Final 4/4/2024 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 4/4/2024 Approved CRAIG VAUGHAN
HVAC-Final 4/4/2024 Approved CRAIG VAUGHAN
MERV13>=Final 4/4/2024 Approved CRAIG VAUGHAN
MERV13>=Rough 4/4/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 4/4/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Not Required CRAIG VAUGHAN
Service/Power Release 4/4/2024 Approved CRAIG VAUGHAN
Smoke Detectors 4/4/2024 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/4/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/11/2024 Approved LILIANA PORTILLO
Final 4/11/2024 Corrections Issued LILIANA PORTILLO
Final 5/14/2024 Partial Inspection OSVALDO PARAMO
Final 5/22/2024 OK to Issue CofO LILIANA PORTILLO