1451 W CARROLL AVE 90026

Certificate Information: 1451 W CARROLL AVE 90026

Application / Permit
21010-10000-06149
Plan Check / Job No.
B21LA22207
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 8/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 DANIEL YIP
Corrections Issued 12/27/2021 DANIEL YIP
Quality Review Completed 12/27/2021 PRANITA SHAH
Plan Check Approved 3/9/2022 DANIEL YIP
Issued 3/16/2022 APPLICANT
CofO in Progress 7/26/2023 THOMAS LOGRASSO
Permit Finaled 8/13/2023 DEROLD HAUFF
CofO Issued 8/13/2023 DEROLD HAUFF
Permit Finaled 8/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/7/2022 KHOUNG LE
Tenant Habitability Plan Cleared 1/7/2022 PHILLIP MUNGUIA
Grading Pre-Inspection Cleared 1/10/2022 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 1/26/2022 KHOUNG LE
Sewer availability Cleared 1/26/2022 KHOUNG LE
HPOZ Cleared 2/4/2022 CHRISTINA PARK
Low Impact Development Cleared 2/4/2022 ANTHONY VARGAS
GPI Written Notices Cleared 2/22/2022 DANIEL YIP
Roof/Waste drainage to street Cleared 2/23/2022 AMAAN MALIK

Contact Information

Contractor Axe Construction Inc; Lic. No.: 1069232-B       ,
Engineer Watters,, Joel David; Lic. No.: C78342 74111 CACTUS WAY      TWENTYNINE PALMS, CA 92277

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/1/2022 Partial Inspection THOMAS LOGRASSO
PLUMBING-Rough 4/11/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 4/13/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 4/13/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 4/18/2022 Conditional Approval THOMAS LOGRASSO
Gas Test 5/4/2022 Partial Approval THOMAS LOGRASSO
Sewer 5/4/2022 Partial Approval THOMAS LOGRASSO
Underground Mechanical 5/4/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/9/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Partial Approval THOMAS LOGRASSO
Special/Order Compliance 5/25/2022 Corrections Issued RYAN SALAZAR
Sewer 6/2/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Corrections Issued THOMAS LOGRASSO
Deputy Wood Construction 6/14/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 8/1/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 8/1/2022 Partial Approval THOMAS LOGRASSO
MERV13>=Rough 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/1/2022 Partial Approval THOMAS LOGRASSO
Sewer 8/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 8/1/2022 No Access for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 9/15/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 9/15/2022 Approved THOMAS LOGRASSO
HVAC-Rough 9/15/2022 Approved THOMAS LOGRASSO
MERV13>=Rough 9/15/2022 Approved THOMAS LOGRASSO
PLUMBING-Rough 9/15/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 11/28/2022 Corrections Issued THOMAS LOGRASSO
Insulation 11/28/2022 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 11/28/2022 Partial Approval THOMAS LOGRASSO
Shower Pan 11/28/2022 Approved THOMAS LOGRASSO
Drywall Nailing 12/13/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 12/13/2022 Partial Approval THOMAS LOGRASSO
Final 5/19/2023 Corrections Issued THOMAS LOGRASSO
MERV13>=Final 5/19/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 5/19/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/5/2023 Approved RUBEN SALAS
Drywall Nailing 6/5/2023 Approved RUBEN SALAS
ELECTRICAL-Final 6/5/2023 Conditional Approval RUBEN SALAS
Final 6/5/2023 Not Ready for Inspection RUBEN SALAS
HVAC-Final 6/5/2023 Approved RUBEN SALAS
PLUMBING-Final 6/5/2023 Approved RUBEN SALAS
Service/Power Release 6/5/2023 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Final 6/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 6/14/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 7/24/2023 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 7/24/2023 Approved THOMAS LOGRASSO