1921 W 79TH ST 90047

Certificate Information: 1921 W 79TH ST 90047

Application / Permit
21010-10000-06147
Plan Check / Job No.
B21LA22205
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Minye to screen counter. Attn: Monica. Permit to Install a RADCO Approved Factory Built Housing Unit over a raised floor foundation per LADBS ADU Standard Plan ADU29. Factory Built Housing per RAD-31-1030. ADU Floor Area: 315.72 SF, Width: 11’-8”, Length: 27’-10”, Height: 13’-8 1/2”. RADCO Stamped FBH Plans Not Subject to LADBS Review or Fees (P/BC-2020-112)
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 5/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2021 APPLICANT
Assigned to Plan Check Engineer 12/14/2021 JOE VO
Corrections Issued 12/14/2021 JOE VO
Applicant returned to address corrections 1/11/2022 JOE VO
Plan Check Approved 2/10/2022 JOE VO
Issued 2/14/2022 APPLICANT
CofO in Progress 4/17/2023 ENRIQUE MIRELES
Permit Finaled 5/17/2023 DEROLD HAUFF
CofO Issued 5/17/2023 DEROLD HAUFF
Permit Finaled 5/17/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/4/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 1/4/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/12/2022 AMAAN MALIK
Sewer availability Cleared 1/12/2022 AMAAN MALIK
Construction near power lines Cleared 2/1/2022 TINA MIRANDA

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/31/2022 Approved ENRIQUE MIRELES
Underground Mechanical 3/31/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/13/2022 Approved ENRIQUE MIRELES
Sewer 4/20/2022 Approved ENRIQUE MIRELES
Underground Mechanical 4/20/2022 Approved ENRIQUE MIRELES
HVAC-Rough 5/19/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Not Ready ENRIQUE MIRELES
ELECTRICAL-Final 9/6/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 9/21/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 9/21/2022 Approved ENRIQUE MIRELES
Final 9/21/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 9/21/2022 Approved ENRIQUE MIRELES
HVAC-Final 9/21/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 9/21/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/21/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 9/21/2022 Approved ENRIQUE MIRELES
Final 12/20/2022 Corrections Issued ENRIQUE MIRELES
Service/Power Release 12/20/2022 Not Ready for Inspection ENRIQUE MIRELES
Final 3/23/2023 Corrections Issued ENRIQUE MIRELES
Service/Power Release 3/23/2023 Not Ready for Inspection ENRIQUE MIRELES
Final 4/14/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 4/14/2023 Approved ENRIQUE MIRELES