1910 S BUCKINGHAM ROAD 90016

Certificate Information: 1910 S BUCKINGHAM ROAD 90016

Application / Permit
21010-10000-06113
Plan Check / Job No.
B21LA22113
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NFPA 13D FIRE SPRINKLERS REQUIRED. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER STANDARD PLAN ADU27 AND LAMC 12.22 A.33 (c)-(d). The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 3/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/20/2021 KEVIN MORALES
Corrections Issued 12/20/2021 KEVIN MORALES
Applicant returned to address corrections 1/11/2022 KEVIN MORALES
Applicant returned to address corrections 2/7/2022 KEVIN MORALES
Applicant returned to address corrections 2/16/2022 KEVIN MORALES
Applicant returned to address corrections 3/31/2022 KEVIN MORALES
Applicant returned to address corrections 4/4/2022 KEVIN MORALES
Applicant returned to address corrections 4/29/2022 KEVIN MORALES
Plan Check Approved 7/26/2023 KEVIN MORALES
Issued 7/26/2023 APPLICANT
CofO in Progress 3/17/2026 JUSTIN HAWLEY
Permit Finaled 3/19/2026 DEROLD HAUFF
CofO Issued 3/19/2026 DEROLD HAUFF
Permit Finaled 3/19/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/10/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/2/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 3/2/2022 WALLIE JONG
Sewer availability Cleared 3/8/2022 WALLIE JONG

Contact Information

Contractor Seagull Construction & Development; Lic. No.: 1073738-B       ,
Engineer Benuska,, Kalman Van; Lic. No.: S3504 950 S GRAND AVE 4TH FLOOR      LOS ANGELES, CA 90015

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/22/2023 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 10/2/2023 Approved CALEB MEISTER
Footing/Foundation/Slab 10/2/2023 Approved CALEB MEISTER
Underground Mechanical 10/2/2023 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 12/4/2023 Approved JUSTIN HAWLEY
PLUMBING-Rough 12/4/2023 Corrections Issued JUSTIN HAWLEY
Gas Test 12/5/2023 Approved JUSTIN HAWLEY
HVAC-Rough 12/5/2023 Approved JUSTIN HAWLEY
PLUMBING-Rough 12/5/2023 Approved JUSTIN HAWLEY
Shower Pan 12/5/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 12/13/2023 Approved JUSTIN HAWLEY
Green Building Rough 12/13/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/13/2023 Partial Approval JUSTIN HAWLEY
Special/Order Compliance 12/13/2023 Corrections Issued JUSTIN HAWLEY
Verify Sprinkler Sign Off 12/13/2023 Approved JUSTIN HAWLEY
Wood Frame 12/13/2023 Approved JUSTIN HAWLEY
Drywall Nailing 1/11/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/11/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 6/6/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Final 6/6/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 6/17/2024 Approved JUSTIN HAWLEY
Final 6/17/2024 Corrections Issued JUSTIN HAWLEY
HVAC-Final 6/27/2024 Approved JUSTIN HAWLEY
Final 3/17/2026 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 3/17/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 3/17/2026 Approved JUSTIN HAWLEY
Smoke Detectors 3/17/2026 Approved JUSTIN HAWLEY