652-654 1/2 S PENRITH DR 90023
Certificate Information: 652-654 1/2 S PENRITH DR 90023
- Application / Permit
- 21010-10000-06101
- Plan Check / Job No.
- B21LA22099
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2-STORY ADDITION AND CONVERSION FROM SINGLE FAMILY DWELLING TO DUPLEX WITH ATTACHED ADU.
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2021 | ALBERT SERVIN |
| Plans on Hold | 12/21/2021 | BILL STUTSMAN |
| Hold Released | 1/20/2022 | EUGENE BARBEAU |
| Corrections Issued | 1/25/2022 | ALBERT SERVIN |
| Quality Review Completed | 1/26/2022 | PETER KIM |
| Building Plans Picked Up | 1/31/2022 | APPLICANT |
| Applicant returned to address corrections | 3/22/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 6/29/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 7/1/2022 | ALBERT SERVIN |
| Plan Check Approved | 7/20/2022 | ALBERT SERVIN |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 10/1/2025 | FREDDIE RIVERA |
| Permit Finaled | 10/1/2025 | DEROLD HAUFF |
| CofO Issued | 10/1/2025 | DEROLD HAUFF |
| Permit Finaled | 10/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 1/18/2022 | JASON SHEETS |
| GPI Written Notices | Cleared | 1/21/2022 | ALBERT SERVIN |
| Address approval | Cleared | 2/10/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | CINDY QI |
| Sewer availability | Cleared | 2/15/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 6/17/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/23/2022 | CINDY QI |
Contact Information
| Architect | Otoniel, Solis; Lic. No.: C34216 | , |
| Contractor | Stay Forever Construction Corporation; Lic. No.: 986055-B | 27138 CHERRY LAUREL PL CANYON COUNTRY, CA 91387 |
| Engineer | Behshid,, Farshid; Lic. No.: S4585 | 10866 WIMER COUNTRY ROAD SUNLAND, CA 91040 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/13/2023 | Partial Approval | FREDDIE RIVERA |
| Deputy Methane Barrier | 5/5/2023 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Barrier | 5/10/2023 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 5/10/2023 | Approved | FREDDIE RIVERA |
| Deputy Methane Barrier | 5/16/2023 | Conditional Approval | FREDDIE RIVERA |
| Deputy Methane Barrier | 5/17/2023 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/22/2023 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 5/22/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/24/2024 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 4/24/2024 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 4/24/2024 | Approved | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 4/24/2024 | Corrections Issued | SCOTT FINNILA |
| Shower Pan | 4/24/2024 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/30/2024 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/30/2024 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 4/30/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/30/2024 | Partial Approval | FREDDIE RIVERA |
| Insulation | 5/6/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 5/21/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 5/21/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 5/21/2024 | Approved | JUSTIN HAWLEY |
| Shower Pan | 5/21/2024 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 5/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 3/20/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 3/20/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 3/20/2025 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 3/20/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 3/20/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 3/20/2025 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Final | 3/20/2025 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 3/20/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 3/20/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 3/20/2025 | Corrections Issued | FREDDIE RIVERA |
| Smoke Detectors | 3/20/2025 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 3/20/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 5/1/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 5/1/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 5/1/2025 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 6/12/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 6/16/2025 | OK to Issue CofO | FREDDIE RIVERA |