9613 1/2 S ANZAC AVE 90002
Certificate Information: 9613 1/2 S ANZAC AVE 90002
- Application / Permit
- 21010-10000-06098
- Plan Check / Job No.
- B21LA22091
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). COMPLY WITH DEPARTMENT ORDER effective date 06/17/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- Issued on 3/25/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | KEVIN MORALES |
| Corrections Issued | 12/16/2021 | KEVIN MORALES |
| Plan Check Approved | 1/12/2022 | KEVIN MORALES |
| Issued | 3/25/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 12/30/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 11/4/2024 | Corrections Issued | KEITH EDGHILL |
| Footing/Foundation/Slab | 4/24/2025 | Conditional Approval | KEITH EDGHILL |
| BUILDING-Rough-Frame | 5/13/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Rough | 5/13/2025 | Not Ready for Inspection | KEITH EDGHILL |
| PLUMBING-Rough | 5/13/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Rough-Elec/Plmb/HVAC | 5/13/2025 | Not Ready for Inspection | KEITH EDGHILL |
| BUILDING-Rough-Frame | 5/15/2025 | Not Ready for Inspection | KEITH EDGHILL |
| ELECTRICAL-Rough | 5/15/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Rough | 5/15/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Insulation | 5/15/2025 | Not Ready for Inspection | KEITH EDGHILL |
| PLUMBING-Rough | 5/15/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Rough-Elec/Plmb/HVAC | 5/15/2025 | Not Ready for Inspection | KEITH EDGHILL |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | KEITH EDGHILL |
| ELECTRICAL-Rough | 5/21/2025 | Approved | KEITH EDGHILL |
| Green Building Rough | 5/21/2025 | Approved | KEITH EDGHILL |
| HVAC-Rough | 5/21/2025 | Approved | KEITH EDGHILL |
| Insulation | 5/21/2025 | Approved | KEITH EDGHILL |
| PLUMBING-Rough | 5/21/2025 | Approved | KEITH EDGHILL |
| Drywall Nailing | 5/28/2025 | Conditional Approval | KEITH EDGHILL |
| Interior/Exterior Lathing | 6/5/2025 | Partial Approval | KEITH EDGHILL |
| Shower Pan | 6/12/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | BRIAN CHRISTIAN |
| Shower Pan | 6/27/2025 | Approved | KEITH EDGHILL |
| Drywall Nailing | 8/5/2025 | Approved | KEITH EDGHILL |
| Final | 8/5/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 8/5/2025 | Not Ready for Inspection | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 8/5/2025 | SGSOV Not Ready | KEITH EDGHILL |
| Smoke Detectors | 8/5/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Final | 9/17/2025 | Corrections Issued | KEITH EDGHILL |
| Green Building Final | 9/17/2025 | Corrections Issued | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Not Ready | KEITH EDGHILL |
| Smoke Detectors | 9/17/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 10/7/2025 | Corrections Issued | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Approved | KEITH EDGHILL |
| Smoke Detectors | 10/7/2025 | Approved | KEITH EDGHILL |
| Final | 10/15/2025 | Corrections Issued | KEITH EDGHILL |
| Green Building Final | 10/15/2025 | Conditional Approval | KEITH EDGHILL |
| Final | 10/21/2025 | Conditional Approval | KEITH EDGHILL |
| Green Building Final | 10/21/2025 | Approved | KEITH EDGHILL |
| ELECTRICAL-Final | 10/28/2025 | Approved | KEITH EDGHILL |
| HVAC-Final | 10/28/2025 | Approved | KEITH EDGHILL |
| PLUMBING-Final | 10/28/2025 | Approved | KEITH EDGHILL |