11100 W PEORIA ST 91352

Certificate Information: 11100 W PEORIA ST 91352

Application / Permit
21010-10000-06085
Plan Check / Job No.
B21LA22029
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
DEFERRED SUBMITTAL TO PERMIT #21010-10000-02256" FOUNDATION ONLY PERMIT FOR MICROPILES OF FOUNDATIONS. ( FOUNDATION ONLY PERMIT # 21010-10002-02256)
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
Permit Finaled on 9/12/2024

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 GARO TELMI
Corrections Issued 1/7/2022 GARO TELMI
Quality Review Completed 1/12/2022 KEN GILL
Plan Check Approved 2/4/2022 GARO TELMI
Issued 2/18/2022 APPLICANT
Building Plans Picked Up 2/22/2022 APPLICANT
Permit Finaled 9/12/2024 DANNY RODRIGUEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Bastien,, Gary L; Lic. No.: C11164 15661 RED HILL AVENUE SUITE 150      TUSTIN, CA 92780
Contractor Snyder Langston Llc; Lic. No.: 1019188-B 17962 COWAN      IRVINE, CA 92614
Engineer Benson,, Thomas Clifford; Lic. No.: GE2091 645 W LA CROSSE ST      GLENDORA, CA 91741
Engineer Cocke,, David Winbern; Lic. No.: S3005 19210 S VERMONT AVENUE BLDNG B SUITE 210      GARDENA, CA 90248
Engineer Rieke,, Axel Dieter; Lic. No.: C71407 2900 22ND ST 13      SAN FRANCISCO, CA 94110
Engineer Siegel,, Timothy Carl; Lic. No.: C78792 1808 NORTHSHORE HILLS E      KNOXVILLE, TN 37922
Engineer Vandervis,, Jacob; Lic. No.: C46301 701 NORTH PARKCENTER DR      SANTA ANA, CA 92705

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/28/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/1/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/2/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/3/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/4/2022 Conditional Approval DANNY RODRIGUEZ
Piling/Pier/Caisson 4/12/2022 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 4/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/13/2022 Conditional Approval DANNY RODRIGUEZ
Piling/Pier/Caisson 4/14/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/15/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/19/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/20/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/21/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/25/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/26/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/27/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 4/29/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 5/2/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 5/3/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 5/4/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 5/5/2022 Partial Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 5/6/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/17/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 5/17/2022 Partial Approval DANNY RODRIGUEZ
Piling/Pier/Caisson 5/17/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/18/2022 Conditional Approval KENNETH ROBERTS
Piling/Pier/Caisson 5/18/2022 Partial Approval KENNETH ROBERTS
Deputy Reinf. Concrete 6/8/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/14/2022 Approved DANNY RODRIGUEZ
Deputy Methane Barrier 6/28/2022 Approved DANNY RODRIGUEZ
Deputy Methane Barrier 6/29/2022 Approved DANNY RODRIGUEZ
Deputy Methane Barrier 6/30/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Methane Barrier 7/1/2022 Conditional Approval DANNY RODRIGUEZ