927 E 118TH DR 90059

Certificate Information: 927 E 118TH DR 90059

Application / Permit
21010-10000-06065
Plan Check / Job No.
B21LA21948
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADDITION TO (E) GARAGE TO BE CONVERTED INTO A DETACHED ADU
Permit Issued
Issued on 9/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2021 APPLICANT
Assigned to Plan Check Engineer 12/8/2021 FERNANDO FLORES
Corrections Issued 12/8/2021 FERNANDO FLORES
Plan Check Approved 2/16/2022 DANIEL SANJUAN
Building Plans Picked Up 2/18/2022 APPLICANT
Issued 9/28/2022 APPLICANT
CofO in Progress 3/29/2024 BEN MOLSTAD
CofO Issued 4/1/2024 ANSON MAGLASANG
Permit Finaled 4/1/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/28/2021 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/28/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/20/2022 AMAAN MALIK
Sewer availability Cleared 1/20/2022 AMAAN MALIK
Construction near power lines Cleared 2/7/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/27/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 10/28/2022 Partial Approval JOHN KLARIN
PLUMBING-Rough 10/28/2022 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 11/7/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/10/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 1/10/2023 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 1/10/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 2/2/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 2/2/2023 Approved JOHN KLARIN
Green Building Rough 2/2/2023 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 2/2/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 2/2/2023 Approved JOHN KLARIN
Insulation 2/28/2023 Approved JOHN KLARIN
Drywall Nailing 3/20/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 6/13/2023 Approved JOHN KLARIN
Gas Test 6/13/2023 Approved JOHN KLARIN
PLUMBING-Rough 6/13/2023 Approved JOHN KLARIN
Underground Mechanical 6/20/2023 Partial Approval JAMES CHAVEZ
Sewer 6/26/2023 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 3/4/2024 Approved BEN MOLSTAD
Final 3/4/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Final 3/4/2024 Approved BEN MOLSTAD
Green Building Rough 3/4/2024 Approved BEN MOLSTAD
MERV13>=Final 3/4/2024 Approved BEN MOLSTAD
MERV13>=Rough 3/4/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 3/4/2024 Not Ready for Inspection BEN MOLSTAD
Final 3/14/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 3/14/2024 Approved BEN MOLSTAD
Final 3/20/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Approved BEN MOLSTAD
ELECTRICAL-Final 3/28/2024 Approved BEN MOLSTAD
Final 3/28/2024 OK to Issue CofO BEN MOLSTAD
HVAC-Final 3/28/2024 Approved BEN MOLSTAD
Service/Power Release 3/29/2024 Approved BEN MOLSTAD