3113 W HOLLYDALE DR 90039

Certificate Information: 3113 W HOLLYDALE DR 90039

Application / Permit
21010-10000-06041
Plan Check / Job No.
B21LA21811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 10/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 CARLOS MONTES
Corrections Issued 12/11/2021 CARLOS MONTES
Quality Review Completed 12/14/2021 HERNAN ARREOLA
Applicant returned to address corrections 2/2/2022 CARLOS MONTES
Applicant returned to address corrections 2/24/2022 CARLOS MONTES
Plan Check Approved 5/6/2022 CARLOS MONTES
Issued 5/9/2022 APPLICANT
CofO in Progress 10/5/2022 HAMIK HARTOUNIAN
Permit Finaled 10/14/2022 DEROLD HAUFF
CofO Issued 10/14/2022 DEROLD HAUFF
Permit Finaled 10/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 12/29/2021 RIDWAN HARDY
Address approval Cleared 1/11/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/11/2022 JEANIE LAM
Sewer availability Cleared 1/11/2022 JEANIE LAM
Low Impact Development Cleared 3/29/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 4/28/2022 JEANIE LAM

Contact Information

Contractor Hy Construction Co; Lic. No.: 680979-B       ,
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2022 Partial Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
PLUMBING-Rough 6/2/2022 Partial Approval SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 6/6/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/6/2022 Approved HAMIK HARTOUNIAN
Sewer 6/6/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 6/24/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 6/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 6/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 6/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 6/29/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 6/29/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/5/2022 Approved HAMIK HARTOUNIAN
Shower Pan 7/5/2022 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 7/5/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/6/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/6/2022 Approved HAMIK HARTOUNIAN
Gas Test 7/6/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 7/6/2022 Approved HAMIK HARTOUNIAN
Shower Pan 7/6/2022 Conditional Approval HAMIK HARTOUNIAN
Wood Frame 7/6/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/11/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/15/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 7/15/2022 Approved HAMIK HARTOUNIAN
Insulation 7/15/2022 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 7/15/2022 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 7/15/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/22/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 7/22/2022 Approved HAMIK HARTOUNIAN
Insulation 7/22/2022 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 7/22/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/29/2022 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 8/1/2022 Approved HAMIK HARTOUNIAN
Gas Test 8/1/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 8/1/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 8/23/2022 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 9/22/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 9/22/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Final 9/22/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 9/27/2022 Approved HAMIK HARTOUNIAN
Final 9/27/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 9/27/2022 Approved HAMIK HARTOUNIAN
MERV13>=Final 9/27/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 9/27/2022 Not Required HAMIK HARTOUNIAN
Smoke Detectors 9/27/2022 Corrections Issued HAMIK HARTOUNIAN
Final 9/30/2022 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 9/30/2022 Approved HAMIK HARTOUNIAN
Final 10/5/2022 OK to Issue CofO HAMIK HARTOUNIAN