11217 W COHASSET ST 91352
Certificate Information: 11217 W COHASSET ST 91352
- Application / Permit
- 21010-10000-06032
- Plan Check / Job No.
- B21LA21769
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22 A.33(C) AND (D)
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 6/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | SUNMIN LEE |
| Corrections Issued | 12/20/2021 | SUNMIN LEE |
| Quality Review Completed | 12/28/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/4/2022 | APPLICANT |
| Applicant returned to address corrections | 8/11/2022 | SUNMIN LEE |
| Plan Check Approved | 8/23/2022 | SUNMIN LEE |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 6/3/2026 | JOSE AVILA |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/8/2022 | RIDWAN HARDY |
| Address approval | Cleared | 3/19/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/23/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 4/14/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 4/18/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/22/2022 | Approved | JORDAN KUTZLY |
| PLUMBING-Rough | 11/22/2022 | Approved | JORDAN KUTZLY |
| BUILDING-Rough-Frame | 12/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 12/6/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/13/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 12/13/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 1/9/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 1/9/2023 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/9/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/30/2023 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 1/30/2023 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/30/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 2/14/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 2/14/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/14/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/26/2023 | Approved | JOHN HAYES |
| Shower Pan | 6/26/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 7/6/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/6/2023 | Approved | JENNIFER RABUCHIN |
| Sewer | 5/21/2024 | Approved | ROBERT GOLD |
| Underground Mechanical | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 6/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/25/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/2/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 12/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 12/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 12/2/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 12/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 12/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 12/24/2025 | Corrections Issued | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 12/29/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/31/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/31/2025 | SGSOV Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/1/2026 | Approved | JOSE AVILA |
| Final | 6/1/2026 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 6/1/2026 | Approved | JOSE AVILA |
| Service/Power Release | 6/1/2026 | Approved | JOSE AVILA |
| Smoke Detectors | 6/1/2026 | Approved | JOSE AVILA |