1568 W VERNON AVE 90062
Certificate Information: 1568 W VERNON AVE 90062
- Application / Permit
- 21010-10000-06027
- Plan Check / Job No.
- B21LA21751
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 17 UNITS (100% AFFORDABLE HOUSING( APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT TIER 4 (SINCE 100% AFF.) TOC WITH BASE INCENTIVES
- Permit Issued
- Issued on 10/9/2023
- Issuing Office
- Current Status
- Issued on 10/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | MANUEL MONTUFAR |
| Corrections Issued | 12/9/2021 | MANUEL MONTUFAR |
| Quality Review Completed | 12/10/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/9/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 8/11/2022 | MANUEL MONTUFAR |
| Plan Check Approved | 9/6/2023 | MANUEL MONTUFAR |
| Issued | 10/9/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2021 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 12/16/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2021 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 12/23/2021 | ADALBERTO VERA |
| Bicycle Parking | Cleared | 1/20/2022 | JEREMY CHOK |
| Highway dedication | Cleared | 1/28/2022 | WALLIE JONG |
| Trees in Parkway | Cleared | 2/2/2022 | ADALBERTO VERA |
| Building over 36-ft | Cleared | 5/18/2022 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 6/27/2022 | MIGUEL GAMBOA |
| Frnt yard landscape/Water mgmt | Cleared | 12/1/2022 | SHASHA YU |
| Opn space landscape/Water mgmt | Cleared | 12/1/2022 | SHASHA YU |
| Low Impact Development | Cleared | 12/8/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | WALLIE JONG |
| Permit | Cleared | 1/25/2023 | WALLIE JONG |
| Sewer availability | Cleared | 1/25/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 2/1/2023 | LAVEON RIDER |
| Fire Marshal Fire Life Safety | Cleared | 2/3/2023 | SARAH ZHANG |
| Community Plan Implem. Overlay | Cleared | 2/14/2023 | WALTER RAMIREZ |
| Construction near power lines | Cleared | 2/14/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/14/2023 | WALTER RAMIREZ |
| Community Plan Implem. Overlay | Cleared | 3/2/2023 | COLLINS ALLAN |
| Community Plan Implem. Overlay | Cleared | 3/21/2023 | RAFAEL FONTES |
| Density Bonus 12.22.A.31 | Cleared | 5/17/2023 | LOUIE MILLER |
| Green Code | Cleared | 7/21/2023 | MANUEL MONTUFAR |
| DAS Clearance | Cleared | 9/6/2023 | MANUEL MONTUFAR |
Contact Information
| Contractor | Ndrbuilds Inc; Lic. No.: 508255-B | , |
| Engineer | Parvini,, Mehdi; Lic. No.: C63186 | 1226 SOUZA DRIVE EL DORADO HILLS, CA 95762 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/30/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 2/26/2024 | Partial Approval | LARRY ARNICK |
| Deputy Wood Construction | 3/26/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 3/27/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 3/27/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 4/15/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 4/15/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Deputy Wood Construction | 4/29/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 5/1/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Rough | 9/3/2024 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 9/3/2024 | Not Ready for Inspection | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 12/6/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 12/6/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 12/6/2024 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 1/31/2025 | Approved | LARRY ARNICK |
| Green Building Rough | 4/2/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 4/2/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 4/2/2025 | No Access for Inspection | RAFAEL ESPINOZA |
| Insulation | 4/4/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 4/14/2025 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 4/14/2025 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 4/14/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Insulation | 7/28/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 7/28/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 6/5/2026 | Partial Approval | JAMES POWERS |