1568 W VERNON AVE 90062

Certificate Information: 1568 W VERNON AVE 90062

Application / Permit
21010-10000-06027
Plan Check / Job No.
B21LA21751
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 17 UNITS (100% AFFORDABLE HOUSING( APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT TIER 4 (SINCE 100% AFF.) TOC WITH BASE INCENTIVES
Permit Issued
Issued on 10/9/2023
Issuing Office
Current Status
Issued on 10/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/19/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 MANUEL MONTUFAR
Corrections Issued 12/9/2021 MANUEL MONTUFAR
Quality Review Completed 12/10/2021 EUGENE BARBEAU
Applicant returned to address corrections 8/9/2022 MANUEL MONTUFAR
Applicant returned to address corrections 8/11/2022 MANUEL MONTUFAR
Plan Check Approved 9/6/2023 MANUEL MONTUFAR
Issued 10/9/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/16/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 12/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/21/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 12/23/2021 ADALBERTO VERA
Bicycle Parking Cleared 1/20/2022 JEREMY CHOK
Highway dedication Cleared 1/28/2022 WALLIE JONG
Trees in Parkway Cleared 2/2/2022 ADALBERTO VERA
Building over 36-ft Cleared 5/18/2022 CALOSHA APPROVED
Miscellaneous Cleared 6/27/2022 MIGUEL GAMBOA
Frnt yard landscape/Water mgmt Cleared 12/1/2022 SHASHA YU
Opn space landscape/Water mgmt Cleared 12/1/2022 SHASHA YU
Low Impact Development Cleared 12/8/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 12/12/2022 WALLIE JONG
Permit Cleared 1/25/2023 WALLIE JONG
Sewer availability Cleared 1/25/2023 WALLIE JONG
Hydrant and Access approval Cleared 2/1/2023 LAVEON RIDER
Fire Marshal Fire Life Safety Cleared 2/3/2023 SARAH ZHANG
Community Plan Implem. Overlay Cleared 2/14/2023 WALTER RAMIREZ
Construction near power lines Cleared 2/14/2023 WALTER RAMIREZ
Construction within easement Cleared 2/14/2023 WALTER RAMIREZ
Community Plan Implem. Overlay Cleared 3/2/2023 COLLINS ALLAN
Community Plan Implem. Overlay Cleared 3/21/2023 RAFAEL FONTES
Density Bonus 12.22.A.31 Cleared 5/17/2023 LOUIE MILLER
Green Code Cleared 7/21/2023 MANUEL MONTUFAR
DAS Clearance Cleared 9/6/2023 MANUEL MONTUFAR

Contact Information

Contractor Ndrbuilds Inc; Lic. No.: 508255-B       ,
Engineer Parvini,, Mehdi; Lic. No.: C63186 1226 SOUZA DRIVE      EL DORADO HILLS, CA 95762
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/29/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/30/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/26/2024 Partial Approval LARRY ARNICK
Deputy Wood Construction 3/26/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 3/27/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/27/2024 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 4/15/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/15/2024 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 4/29/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 5/1/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/1/2024 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 9/3/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/3/2024 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 12/6/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/6/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 12/6/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 1/31/2025 Approved LARRY ARNICK
Green Building Rough 4/2/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/2/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/2/2025 No Access for Inspection RAFAEL ESPINOZA
Insulation 4/4/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 4/14/2025 Partial Approval RAFAEL ESPINOZA
Green Building Rough 4/14/2025 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/14/2025 Partial Inspection RAFAEL ESPINOZA
Insulation 7/28/2025 Not Ready for Inspection ALFREDO LOPEZ
Pre-Inspection 7/28/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 6/5/2026 Partial Approval JAMES POWERS