5521 S ST ANDREWS PL 90062
Certificate Information: 5521 S ST ANDREWS PL 90062
- Application / Permit
- 21010-10000-06023
- Plan Check / Job No.
- B21LA21716
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Construction of HCD approved and inspected Factory Built Housing ADU. ADU to be fully completed in Factory and installed on Concrete t-footing foundation, connected to site utilities. 336 sq ft LADBS ADU3 Approved plan.
- Permit Issued
- Issued on 3/28/2022
- Issuing Office
- Current Status
- CofO Issued on 12/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | CARLOS MONTES |
| Corrections Issued | 12/4/2021 | CARLOS MONTES |
| Quality Review Completed | 12/14/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 1/13/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 2/22/2022 | CARLOS MONTES |
| Plan Check Approved | 3/22/2022 | CARLOS MONTES |
| Issued | 3/28/2022 | APPLICANT |
| CofO in Progress | 11/2/2022 | SABAS ALONSO |
| Permit Finaled | 12/7/2022 | DEROLD HAUFF |
| CofO Issued | 12/7/2022 | DEROLD HAUFF |
| Permit Finaled | 12/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/9/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 2/10/2022 | JEANETTE VONG |
Contact Information
| Contractor | Abodu Inc; Lic. No.: 1073522-B | , |
| Engineer | Denio,, Jordan Paul; Lic. No.: C74796 | 2778 CLAPHAM LN MINDEN, NV 89423 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2022 | Corrections Issued | SABAS ALONSO |
| Sewer | 5/13/2022 | Approved | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/23/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | SABAS ALONSO |
| Final | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 7/15/2022 | Approved | SABAS ALONSO |
| Green Building Final | 7/15/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 7/15/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 7/15/2022 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 7/15/2022 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 7/15/2022 | Approved | SABAS ALONSO |
| Final | 7/26/2022 | Conditional Approval | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 7/26/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/1/2022 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 11/1/2022 | Approved | SABAS ALONSO |