12307 W TERRA BELLA ST 91331
Certificate Information: 12307 W TERRA BELLA ST 91331
- Application / Permit
- 21010-10000-05994
- Plan Check / Job No.
- B19LA17411
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- New accessory office and kitchen building for Church per ZA-2016-4986-CU-ZV-ZAA-F
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Metro
- Current Status
- Issued on 12/13/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | ALBERT SERVIN |
| Corrections Issued | 9/16/2019 | ALBERT SERVIN |
| Quality Review Completed | 9/18/2019 | KEN GILL |
| Building Plans Picked Up | 9/20/2019 | APPLICANT |
| Green Plans Picked Up | 9/20/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/1/2019 | APPLICANT |
| Applicant returned to address corrections | 11/16/2021 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/12/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/14/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/19/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/21/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 11/10/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 12/9/2022 | ALBERT SERVIN |
| Plan Check Approved | 12/13/2022 | ALBERT SERVIN |
| Issued | 12/13/2022 | APPLICANT |
| TCO Issued (Expire Date: 05-23-2026) | 11/24/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 12/19/2021 | ALBERT SERVIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | LEE GUILBEAUX |
| Internal circulation | Cleared | 1/4/2022 | DURRE SHAMSI |
| Sewer availability | Cleared | 1/12/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/31/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 5/18/2022 | ALBERT SERVIN |
| Address approval | Cleared | 5/20/2022 | JOHN LIN |
| Highway dedication | Cleared | 6/10/2022 | CARLOS AGUILERA |
| Permit | Cleared | 6/10/2022 | CARLOS AGUILERA |
| Fire Marshall Fire Life Safety | Cleared | 8/10/2022 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 8/26/2022 | ALBERT SERVIN |
| Certificate of Compliance | Cleared | 9/20/2022 | DALIA MOKAYED |
| Grading in hillside | Cleared | 9/20/2022 | DALIA MOKAYED |
| Miscellaneous | Cleared | 9/20/2022 | DALIA MOKAYED |
| Prkng lot landscape/Water mgmt | Cleared | 9/20/2022 | DALIA MOKAYED |
| Tract Map conditions | Cleared | 9/20/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 9/20/2022 | DALIA MOKAYED |
| Low Impact Development | Cleared | 10/7/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | COLIN LOREDO |
Contact Information
| Architect | Kluger,, Charles Edward; Lic. No.: C24283 | 560 N WESTERN AVE, 2ND FLOOR LOS ANGELES, CA 90004 |
| Contractor | Hoffman & Associates Building Corporation; Lic. No.: 421531-B | 7120 HAYVENHURST AVE STE 110 VAN NUYS, CA 91406 |
| Engineer | Hill,, Edward Foster; Lic. No.: GE2126 | 27865 AMBERWOOD LANE VALENCIA, CA 91354 |
| Engineer | Hodali,, Ramzi; Lic. No.: S3552 | 3830 DIXIE CANYON AVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/10/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Grading Pre-Inspection | 5/23/2023 | Partial Inspection | ROBERT DAVIS |
| Deputy Reinf. Concrete | 6/20/2023 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 6/20/2023 | Partial Approval | DANNY RODRIGUEZ |
| Piling/Pier/Caisson | 7/20/2023 | Partial Approval | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Piling/Pier/Caisson | 7/21/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 8/18/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Wood Construction | 9/14/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Wood Construction | 9/29/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 10/3/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/3/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 10/3/2023 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 2/29/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/29/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 2/29/2024 | Corrections Issued | DANNY RODRIGUEZ |
| Green Building Rough | 3/11/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/11/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 3/11/2024 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 3/14/2024 | Approved | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 3/14/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/14/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 3/14/2024 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 3/19/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 3/21/2024 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 4/3/2024 | Partial Approval | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 4/3/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 4/4/2024 | Approved | DANNY RODRIGUEZ |
| Drywall Nailing | 4/16/2024 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 4/16/2024 | Not Ready for Inspection | GREGORY POMISH |
| Drywall Nailing | 4/23/2024 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 1/9/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 1/9/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 1/23/2025 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 1/23/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 1/29/2025 | Conditional Approval | DANNY RODRIGUEZ |
| Final | 4/7/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/7/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 4/7/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 4/7/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/7/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 4/7/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 4/10/2025 | OK for TCO | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/10/2025 | Approved | DANNY RODRIGUEZ |
| Green Building Final | 4/10/2025 | Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 4/10/2025 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/10/2025 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 4/10/2025 | Approved | DANNY RODRIGUEZ |
| Final | 8/12/2025 | Partial Inspection | ANDREW DORSO |
| Final | 9/3/2025 | Corrections Issued | ROBERT DAVIS |
| Special/Order Compliance | 4/15/2026 | Partial Inspection | JOHN KITCKO |
| Special/Order Compliance | 5/8/2026 | Partial Inspection | JOHN KITCKO |