4424 W 63RD PL 90003
Certificate Information: 4424 W 63RD PL 90003
- Application / Permit
- 21010-10000-05951
- Plan Check / Job No.
- B21LA21472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 800 SQFT ADU AT THE REAR OF THE EXISTING S.F.D. PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). TYPE VA CONSTRUCTION
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 5/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | JOE VO |
| Corrections Issued | 11/24/2021 | JOE VO |
| Plan Check Approved | 3/15/2022 | JOE VO |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 5/10/2023 | ENRIQUE MIRELES |
| CofO in Progress | 5/10/2023 | ENRIQUE MIRELES |
| Permit Finaled | 5/16/2023 | DEROLD HAUFF |
| CofO Issued | 5/16/2023 | DEROLD HAUFF |
| Permit Finaled | 5/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2021 | JEANIE LAM |
| Sewer availability | Cleared | 12/28/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 12/29/2021 | ROBERT HUGHES |
| Hydrant and Access approval | Cleared | 2/28/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 3/1/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | JEANETTE VONG |
Contact Information
| Contractor | Frost Construction; Lic. No.: 580847-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/14/2022 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 4/14/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/19/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/19/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/23/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/23/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/23/2022 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 5/26/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/1/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/27/2022 | Approved | HORACE FULTZ |
| Gas Test | 6/27/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 6/27/2022 | Approved | HORACE FULTZ |
| Sewer | 6/27/2022 | Approved | HORACE FULTZ |
| Verify Sprinkler Sign Off | 6/27/2022 | Approved | HORACE FULTZ |
| Insulation | 7/1/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/7/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/27/2022 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Final | 2/24/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/24/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 2/24/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/24/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/24/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/24/2023 | Approved | ENRIQUE MIRELES |
| Final | 4/21/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 4/21/2023 | Approved | ENRIQUE MIRELES |