2815 S CLOVERDALE AVE 90016
Certificate Information: 2815 S CLOVERDALE AVE 90016
- Application / Permit
- 21010-10000-05906
- Plan Check / Job No.
- B21LA21345
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER 12.22 A33 C & D (BLDG D)
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | STARR CHEN |
| Corrections Issued | 12/5/2021 | STARR CHEN |
| Quality Review Completed | 12/14/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| Applicant returned to address corrections | 6/3/2022 | STARR CHEN |
| Applicant returned to address corrections | 7/29/2022 | STARR CHEN |
| Plan Check Approved | 8/25/2022 | STARR CHEN |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 9/26/2024 | ARTHUR NEGRETE |
| CofO in Progress | 9/27/2024 | JONATHAN HOM |
| Permit Finaled | 3/3/2025 | DEROLD HAUFF |
| CofO Issued | 3/3/2025 | DEROLD HAUFF |
| Permit Finaled | 3/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 1/6/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 6/2/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 7/11/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | THAN WIN |
| Construction near power lines | Cleared | 8/24/2022 | TINA MIRANDA |
Contact Information
| Contractor | H T A Construction & Development; Lic. No.: 1044038-B | 3646 LONG BEACH BLVD STE 107 LONG BEACH, CA 90807 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Gentry,, Bryan Douglas; Lic. No.: L6345 | 255 E EASY ST UNIT B SIMI VALLEY, CA 93065 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/7/2023 | Corrections Issued | STUART CHAPMAN |
| Underground Mechanical | 6/8/2023 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 8/14/2023 | Conditional Approval | JOSE AVILA |
| Drywall Nailing | 8/15/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 8/21/2023 | No Access for Inspection | JOSE AVILA |
| Drywall Nailing | 8/22/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Final | 11/21/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/21/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/28/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 12/6/2023 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 12/13/2023 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 12/14/2023 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 12/14/2023 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 12/18/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/26/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 12/26/2023 | Approved | SCOTT FINNILA |
| Wood Frame | 12/26/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 1/4/2024 | Approved | RONNIE MINDANAO |
| Shower Pan | 1/9/2024 | Approved | RONNIE MINDANAO |
| Insulation | 1/16/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/16/2024 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 1/24/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Drywall Nailing | 1/26/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 1/30/2024 | No Access for Inspection | JOSE MACIAS |
| Underground Mechanical | 4/12/2024 | Partial Approval | RICHARD DOCKUS |
| Underground Mechanical | 4/18/2024 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 4/19/2024 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 4/26/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Underground Mechanical | 4/29/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/9/2024 | Corrections Issued | ARTHUR NEGRETE |
| PLUMBING-Final | 8/9/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/13/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 8/13/2024 | Approved | ARTHUR NEGRETE |
| Gas Test | 8/20/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 9/16/2024 | SGSOV Not Ready | ARTHUR NEGRETE |
| Pre-Inspection | 9/17/2024 | Approved | ARTHUR NEGRETE |
| Final | 9/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 9/18/2024 | Approved | ARTHUR NEGRETE |
| Green Building Final | 9/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 9/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 9/18/2024 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 9/20/2024 | Approved | ARTHUR NEGRETE |
| Final | 9/25/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 9/25/2024 | Approved | ARTHUR NEGRETE |