2523 W PLATA ST 90026
Certificate Information: 2523 W PLATA ST 90026
- Application / Permit
- 21010-10000-05899
- Plan Check / Job No.
- B21LA21323
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1,200 SQ FT DETACHED ADU 2 STORY
- Permit Issued
- Issued on 7/3/2022
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | JOE VO |
| Corrections Issued | 12/24/2021 | JOE VO |
| Quality Review Completed | 12/28/2021 | LIPING TENG |
| Applicant returned to address corrections | 4/7/2022 | JOE VO |
| Applicant returned to address corrections | 4/21/2022 | JOE VO |
| Plan Check Approved | 6/6/2022 | JOE VO |
| Issued | 7/3/2022 | APPLICANT |
| CofO in Progress | 5/10/2024 | FREDDIE RIVERA |
| CofO in Progress | 5/10/2024 | FREDDIE RIVERA |
| No Progress | 5/13/2024 | FREDDIE RIVERA |
| CofO in Progress | 5/13/2024 | FREDDIE RIVERA |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2022 | JEANIE LAM |
| Sewer availability | Cleared | 1/13/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 4/5/2022 | KIRK LINKLATER |
| Low Impact Development | Cleared | 5/24/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | JEANIE LAM |
Contact Information
| Contractor | Lightning Construction Company; Lic. No.: 900084-B | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/9/2022 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/27/2022 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Barrier | 9/27/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 9/27/2022 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/4/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 10/4/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 12/13/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/6/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/6/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/6/2023 | Approved | FREDDIE RIVERA |
| Wood Frame | 2/6/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/7/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/7/2023 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/7/2023 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 2/7/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/13/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/13/2023 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/13/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 2/13/2023 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 2/13/2023 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/13/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/15/2023 | Partial Inspection | FREDDIE RIVERA |
| Gas Test | 2/15/2023 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 2/15/2023 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/15/2023 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/21/2023 | Approved | FREDDIE RIVERA |
| Insulation | 2/21/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/21/2023 | Approved | FREDDIE RIVERA |
| Gas Test | 6/12/2023 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 6/12/2023 | Partial Inspection | FREDDIE RIVERA |
| Sewer | 6/12/2023 | Partial Inspection | FREDDIE RIVERA |
| Gas Test | 6/14/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Final | 6/14/2023 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 6/14/2023 | Partial Approval | FREDDIE RIVERA |
| Sewer | 6/14/2023 | Partial Inspection | FREDDIE RIVERA |
| Sewer | 6/21/2023 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 6/21/2023 | Partial Approval | FREDDIE RIVERA |
| Final | 9/6/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 9/6/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 9/6/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 9/6/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 9/6/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 10/16/2023 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Final | 10/16/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 10/16/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 10/16/2023 | Approved | FREDDIE RIVERA |
| Final | 3/8/2024 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 3/8/2024 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 5/13/2024 | Corrections Issued | FREDDIE RIVERA |
| Special/Order Compliance | 8/22/2024 | Approved | FREDDIE RIVERA |