10826 W TABOR ST 90034
Certificate Information: 10826 W TABOR ST 90034
- Application / Permit
- 21010-10000-05894
- Plan Check / Job No.
- B21LA21314
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Accessory Dwelling unit by Installing a two-bedroom RADCO Approved Factory Built Housing Accessory Dwelling Unit over a raised floor foundation. LADBS ADU Standard Plan ADU30. FBH Per: RAD-31-1029. Optional Pre-Cast Foundation per RAD-31-1034. per CA Govt. Code 65852.2(e)(1)(B) The building shall be equipped with an automatic residential fire sprinkler system NFPA13D.
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2021 | MONICA RAMIREZ |
| Corrections Issued | 11/29/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/22/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/11/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/21/2022 | MONICA RAMIREZ |
| Plan Check Approved | 3/19/2022 | JOE VO |
| Issued | 3/23/2022 | APPLICANT |
| CofO in Progress | 3/28/2023 | JOHNNY MIRANDA |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
| CofO Issued | 4/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 1/11/2022 | SAUL GARCIA |
| Miscellaneous | Cleared | 1/18/2022 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 2/15/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/16/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 2/16/2022 | PEDRO AYALA |
| GPI Written Notices | Cleared | 3/19/2022 | JOE VO |
| Grading Pre-Inspection | Cleared | 3/19/2022 | MONICA RAMIREZ |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | , |
| Engineer | Farish,, William Crawford; Lic. No.: C30123 | 19432 CASTLEWOOD CR HUNTINGTON BEACH, CA 92648 |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 1909 S ALMA STREET SAN PEDRO, CA 90731 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Approved | KEVIN SARGSYAN |
| Sewer | 7/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 7/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/22/2022 | No Access for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 7/22/2022 | No Access for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 7/22/2022 | No Access for Inspection | JOHNNY MIRANDA |
| Sewer | 8/15/2022 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 8/15/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/30/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 8/30/2022 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/20/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 10/20/2022 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 10/20/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 2/1/2023 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/1/2023 | Approved | JOHNNY MIRANDA |
| Green Building Final | 2/1/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 2/1/2023 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 2/1/2023 | Approved | JOHNNY MIRANDA |
| Final | 2/27/2023 | Corrections Issued | JOHNNY MIRANDA |
| Final | 3/24/2023 | OK to Issue CofO | JOHNNY MIRANDA |