2240-2242 N ALLESANDRO ST 90039
Certificate Information: 2240-2242 N ALLESANDRO ST 90039
- Application / Permit
- 21010-10000-05883
- Plan Check / Job No.
- B21LA21257
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) SINGLE FAMILY DWELLING PER LAMC 12.22.A.33.(c) AND (e)
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 6/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | DANIEL YIP |
| Corrections Issued | 12/21/2021 | DANIEL YIP |
| Quality Review Completed | 12/22/2021 | LIPING TENG |
| Plan Check Approved | 4/5/2022 | DANIEL YIP |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 4/1/2024 | THOMAS LOGRASSO |
| Permit Finaled | 6/27/2024 | DEROLD HAUFF |
| CofO Issued | 6/27/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2022 | CINDY QI |
| Sewer availability | Cleared | 2/14/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 2/28/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 3/14/2022 | KHAING AYE |
| Frnt yard landscape/Water mgmt | Cleared | 3/22/2022 | RYAN LY |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | CINDY QI |
| GPI Written Notices | Cleared | 4/5/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 4/5/2022 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: C64144 | 29082 MADRID PL CASTAIC, CA 91384 |
| Engineer | Boules,, George Helmy; Lic. No.: NA64144 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/3/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 6/13/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/13/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 6/24/2022 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/29/2022 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 8/19/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Corrections Issued | THOMAS LOGRASSO |
| Wood Frame | 8/25/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 10/27/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/29/2022 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 11/29/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 1/26/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/26/2023 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 1/26/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 2/9/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 2/15/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/8/2023 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Final | 12/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 12/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 12/8/2023 | Approved | THOMAS LOGRASSO |
| Final | 3/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 3/26/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 3/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 3/29/2024 | OK to Issue CofO | THOMAS LOGRASSO |