2240-2242 N ALLESANDRO ST 90039

Certificate Information: 2240-2242 N ALLESANDRO ST 90039

Application / Permit
21010-10000-05883
Plan Check / Job No.
B21LA21257
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) SINGLE FAMILY DWELLING PER LAMC 12.22.A.33.(c) AND (e)
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 DANIEL YIP
Corrections Issued 12/21/2021 DANIEL YIP
Quality Review Completed 12/22/2021 LIPING TENG
Plan Check Approved 4/5/2022 DANIEL YIP
Issued 4/5/2022 APPLICANT
CofO in Progress 4/1/2024 THOMAS LOGRASSO
Permit Finaled 6/27/2024 DEROLD HAUFF
CofO Issued 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/10/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 2/14/2022 CINDY QI
Sewer availability Cleared 2/14/2022 CINDY QI
Hydrant and Access approval Cleared 2/28/2022 CINDY JOSSELYN
Low Impact Development Cleared 3/14/2022 KHAING AYE
Frnt yard landscape/Water mgmt Cleared 3/22/2022 RYAN LY
Roof/Waste drainage to street Cleared 3/22/2022 CINDY QI
GPI Written Notices Cleared 4/5/2022 DANIEL YIP
Grading Pre-Inspection Cleared 4/5/2022 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George Helmy; Lic. No.: C64144 29082 MADRID PL      CASTAIC, CA 91384
Engineer Boules,, George Helmy; Lic. No.: NA64144       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/3/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 6/13/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 6/13/2022 Not Ready for Inspection THOMAS LOGRASSO
Deputy Drilled-In Anchors 6/24/2022 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/29/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 6/29/2022 Approved THOMAS LOGRASSO
Deputy Wood Construction 8/19/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Corrections Issued THOMAS LOGRASSO
Wood Frame 8/25/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 10/27/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 10/27/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 10/27/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 11/29/2022 Partial Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/29/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/26/2023 Approved THOMAS LOGRASSO
Insulation 1/26/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 1/26/2023 Approved THOMAS LOGRASSO
MERV13>=Rough 1/26/2023 Approved THOMAS LOGRASSO
Insulation 2/9/2023 Approved THOMAS LOGRASSO
Drywall Nailing 2/15/2023 Approved THOMAS LOGRASSO
Final 12/8/2023 Corrections Issued THOMAS LOGRASSO
MERV13>=Final 12/8/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 12/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 12/8/2023 Approved THOMAS LOGRASSO
Final 3/26/2024 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 3/26/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 3/26/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 3/29/2024 OK to Issue CofO THOMAS LOGRASSO