4821 W 1ST ST 90004
Certificate Information: 4821 W 1ST ST 90004
- Application / Permit
- 21010-10000-05881
- Plan Check / Job No.
- B21LA21254
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE PORTION OF CARPORT/GARGE INTO DETACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 4/12/2022
- Issuing Office
- Current Status
- CofO Issued on 11/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | CARLOS MONTES |
| Corrections Issued | 11/12/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 1/5/2022 | CARLOS MONTES |
| Plan Check Approved | 4/12/2022 | CARLOS MONTES |
| Issued | 4/12/2022 | APPLICANT |
| CofO in Progress | 8/17/2022 | JEFFREY MEAD |
| Permit Finaled | 11/7/2022 | DEROLD HAUFF |
| CofO Issued | 11/7/2022 | DEROLD HAUFF |
| Permit Finaled | 11/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 12/20/2021 | MELISSA JONES |
| HPOZ | Cleared | 12/20/2021 | MELISSA JONES |
| Hist. Property Cntrct Mgr Appr | Cleared | 12/20/2021 | MELISSA JONES |
| Miscellaneous | Cleared | 12/20/2021 | MELISSA JONES |
| Sewer availability | Cleared | 12/21/2021 | CHRISTOPHER ROCHA |
| Address approval | Cleared | 12/22/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2021 | CHRISTOPHER ROCHA |
| CPC | Cleared | 12/27/2021 | LYDIA CHAPMAN |
| CPC | Cleared | 12/27/2021 | LYDIA CHAPMAN |
| Construction near power lines | Cleared | 3/15/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/11/2022 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 5/11/2022 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Final | 5/23/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 5/26/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 6/3/2022 | Approved | SHAVONNE ESPINOZA |
| Insulation | 8/8/2022 | Approved | JEFFREY MEAD |
| Wood Frame | 8/8/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/17/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/17/2022 | Approved | JEFFREY MEAD |
| Final | 8/17/2022 | OK to Issue CofO | JEFFREY MEAD |
| Gas Test | 8/17/2022 | Approved | JEFFREY MEAD |
| Green Building Final | 8/17/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 8/17/2022 | Approved | JEFFREY MEAD |
| HVAC-Final | 8/17/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 8/17/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 8/17/2022 | Approved | JEFFREY MEAD |