1927 S KELTON AVE 90025
Certificate Information: 1927 S KELTON AVE 90025
- Application / Permit
- 21010-10000-05865
- Plan Check / Job No.
- B21LA21202
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story SFD& attached 2-car garage
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 12/3/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/10/2021 | FARUK SEZER |
| Plan Check Approved | 3/18/2022 | SERGIO GUTIERREZ |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 6/2/2024 | KIRK SANDERS |
| Permit Finaled | 6/11/2024 | DANIEL ORRANTE |
| CofO Issued | 6/11/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/11/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 12/13/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 12/14/2021 | JOSE HERNANDEZ |
| Specific Plan | Cleared | 1/10/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 1/21/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/26/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 2/20/2022 | DWAYNE LAURENT |
| GPI Written Notices | Cleared | 3/18/2022 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 3/18/2022 | SERGIO GUTIERREZ |
Contact Information
| Contractor | M Y Construction Inc; Lic. No.: 1036168-B | 10116 HILLGROVE DRIVE BEVERLY HILLS, CA 90210 |
| Engineer | Khansa,, Eyass Wafik; Lic. No.: C91758 | 2252 JOSIE AVE LONG BEACH, CA 90815 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 9/13/2022 | Conditional Approval | JOHN KIDWELL |
| Underground Mechanical | 9/14/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/16/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/23/2022 | Approved | JOHN KIDWELL |
| Reinforced Concrete Frame | 10/12/2022 | Corrections Issued | EVAN COOPER |
| Deputy Steel/Welding | 10/28/2022 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 11/8/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 11/8/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 11/8/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Wood Frame | 11/8/2022 | Partial Approval | ASHLEY THOMPSON |
| HVAC-Rough | 12/5/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/5/2022 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 12/21/2022 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Steel/Welding | 12/28/2022 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | CLAYTON GRAHAM |
| Special/Order Compliance | 1/20/2023 | Partial Inspection | MICHAEL PELHAM |
| PLUMBING-Rough | 3/20/2023 | Corrections Issued | CLAYTON GRAHAM |
| Special/Order Compliance | 3/20/2023 | Partial Inspection | JESUS PINEDA |
| HVAC-Rough | 3/21/2023 | Not Ready for Inspection | JEREMY TODD |
| BUILDING-Rough-Frame | 3/22/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 3/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 4/5/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 4/26/2023 | Partial Approval | JESUS PINEDA |
| Insulation | 5/9/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 5/12/2023 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 5/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 5/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 5/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 5/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 5/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 5/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/18/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 5/18/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 5/18/2023 | Approved | JESUS PINEDA |
| Insulation | 5/18/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 5/18/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 5/18/2023 | Approved | JESUS PINEDA |
| Insulation | 5/24/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/31/2023 | Approved | JESUS PINEDA |
| Shower Pan | 5/31/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/14/2023 | Approved | MICHAEL PELHAM |
| Gas Test | 10/17/2023 | Approved | BEN MOLSTAD |
| Final | 11/29/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Final | 11/29/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 11/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Service/Power Release | 11/29/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Final | 12/5/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 12/5/2023 | Approved | BEN MOLSTAD |
| HVAC-Final | 12/7/2023 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 12/15/2023 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 12/15/2023 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 12/22/2023 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 12/26/2023 | Approved | BEN MOLSTAD |
| HVAC-Final | 12/29/2023 | Conditional Approval | BEN MOLSTAD |
| Service/Power Release | 2/13/2024 | Approved | MICHAEL PELHAM |
| Final | 4/19/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 4/19/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 4/19/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 5/22/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 5/22/2024 | Approved | KIRK SANDERS |
| Final | 5/24/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 5/31/2024 | OK to Issue CofO | KIRK SANDERS |