5750 S 10TH AVE 90043
Certificate Information: 5750 S 10TH AVE 90043
- Application / Permit
- 21010-10000-05862
- Plan Check / Job No.
- B21LA21192
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 3 car garage to ADU, maintaining existing footprint, setbacks and structural members.
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofO Issued on 12/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/11/2021 | JOE VO |
| Corrections Issued | 11/11/2021 | JOE VO |
| Plan Check Approved | 2/24/2022 | JOE VO |
| Issued | 5/12/2022 | APPLICANT |
| CofO in Progress | 12/15/2022 | ANTHONY EGSON |
| Permit Finaled | 12/22/2022 | DEROLD HAUFF |
| CofO Issued | 12/22/2022 | DEROLD HAUFF |
| Permit Finaled | 12/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2021 | CINDY QI |
| Sewer availability | Cleared | 11/22/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | CINDY QI |
| Redevelopment Project Area | Cleared | 12/9/2021 | DAVID URITA |
| Hydrant and Access approval | Cleared | 2/23/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/14/2022 | Approved | ANTHONY EGSON |
| Sewer | 6/14/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 6/23/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/9/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/12/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 8/12/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/23/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/8/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/8/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 9/27/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 9/27/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 10/4/2022 | Approved | ANTHONY EGSON |
| Insulation | 10/4/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/18/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 11/18/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 11/18/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 11/18/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 11/18/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 11/18/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 11/18/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/8/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/8/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 12/8/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/8/2022 | Approved | ALIZAH MAYAGOITIA |