8143 N CREBS AVE 91335
Certificate Information: 8143 N CREBS AVE 91335
- Application / Permit
- 21010-10000-05855
- Plan Check / Job No.
- B21LA21183
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW STORAGE STRUCTURE
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Current Status
- CofO Issued on 1/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | RAHEL BEYENE |
| Corrections Issued | 11/23/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 1/2/2022 | ZAW HAN |
| Plan Check Approved | 1/4/2022 | ZAW HAN |
| Issued | 1/14/2022 | APPLICANT |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| CofO in Progress | 9/2/2022 | JEFFREY BULL |
| Permit Finaled | 1/20/2023 | JOHN JANSON |
| CofO Issued | 1/20/2023 | JOHN JANSON |
| Permit Finaled | 1/20/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/22/2021 | CARLOS AGUILERA |
Contact Information
| Architect | , ; Lic. No.: C38316 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| SGSOV-Seismic Gas S/O Valve | 2/4/2022 | SGSOV Not Ready | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/10/2022 | Corrections Issued | VINCENT HANLEY |
| Drywall Nailing | 2/10/2022 | Corrections Issued | VINCENT HANLEY |
| Final | 2/10/2022 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/10/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/10/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 2/10/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 2/10/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/10/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Pre-Inspection | 4/22/2022 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/16/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/26/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/2/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/2/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/16/2022 | Approved | JEFFREY BULL |
| Final | 8/16/2022 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 8/16/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 8/16/2022 | Approved | JEFFREY BULL |
| Smoke Detectors | 8/16/2022 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 8/16/2022 | Approved | JEFFREY BULL |