8143 N CREBS AVE 91335

Certificate Information: 8143 N CREBS AVE 91335

Application / Permit
21010-10000-05855
Plan Check / Job No.
B21LA21183
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
NEW STORAGE STRUCTURE
Permit Issued
Issued on 1/14/2022
Issuing Office
Current Status
CofO Issued on 1/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 RAHEL BEYENE
Corrections Issued 11/23/2021 RAHEL BEYENE
Applicant returned to address corrections 1/2/2022 ZAW HAN
Plan Check Approved 1/4/2022 ZAW HAN
Issued 1/14/2022 APPLICANT
Building Plans Picked Up 1/24/2022 APPLICANT
CofO in Progress 9/2/2022 JEFFREY BULL
Permit Finaled 1/20/2023 JOHN JANSON
CofO Issued 1/20/2023 JOHN JANSON
Permit Finaled 1/20/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/22/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/22/2021 CARLOS AGUILERA

Contact Information

Architect , ; Lic. No.: C38316       ,
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Not Ready VINCENT HANLEY
BUILDING-Rough-Frame 2/10/2022 Corrections Issued VINCENT HANLEY
Drywall Nailing 2/10/2022 Corrections Issued VINCENT HANLEY
Final 2/10/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 2/10/2022 Corrections Issued VINCENT HANLEY
Green Building Final 2/10/2022 Corrections Issued VINCENT HANLEY
Green Building Rough 2/10/2022 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 2/10/2022 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 2/10/2022 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 2/10/2022 Not Ready for Inspection VINCENT HANLEY
Pre-Inspection 4/22/2022 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/12/2022 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/16/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/16/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/26/2022 Approved VINCENT HANLEY
Drywall Nailing 6/2/2022 Approved VINCENT HANLEY
Green Building Rough 6/2/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/16/2022 Approved JEFFREY BULL
Final 8/16/2022 OK to Issue CofO JEFFREY BULL
Green Building Final 8/16/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Approved JEFFREY BULL
Service/Power Release 8/16/2022 Approved JEFFREY BULL
Smoke Detectors 8/16/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 8/16/2022 Approved JEFFREY BULL