5112 1/2 W PACKARD ST 90019

Certificate Information: 5112 1/2 W PACKARD ST 90019

Application / Permit
21010-10000-05853
Plan Check / Job No.
B21LA21179
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of existing garage to an ADU.
Permit Issued
Issued on 3/15/2023
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 JOE VO
Corrections Issued 11/11/2021 JOE VO
Applicant returned to address corrections 3/11/2022 JOE VO
Plan Check Approved 4/8/2022 JOE VO
Issued 3/15/2023 APPLICANT
CofO in Progress 8/19/2024 STUART CHAPMAN
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/20/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 12/20/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/3/2022 WALLIE JONG
Sewer availability Cleared 1/3/2022 WALLIE JONG
Construction near power lines Cleared 4/6/2022 RIDWAN HARDY

Contact Information

Architect Chhan,, Danny; Lic. No.: NA37636       ,
Contractor Silva P Construction Inc; Lic. No.: 1061045-B       ,
Engineer Pachunuri,, Nalin Kumar; Lic. No.: NA78970       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/28/2023 Corrections Issued CALEB MEISTER
Footing/Foundation/Slab 4/5/2023 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 4/24/2023 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 4/28/2023 Approved CALEB MEISTER
PLUMBING-Rough 5/9/2023 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/16/2023 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 6/16/2023 Approved STUART CHAPMAN
Green Building Rough 6/16/2023 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 6/16/2023 Approved STUART CHAPMAN
PLUMBING-Rough 6/16/2023 Approved STUART CHAPMAN
Insulation 7/10/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/10/2023 Approved MICHAEL LEWIS
Shower Pan 7/10/2023 Not Ready for Inspection MICHAEL LEWIS
Drywall Nailing 7/24/2023 Approved CALEB MEISTER
Gas Test 10/26/2023 Approved CHARLES BOGHOSKHAN
Sewer 10/26/2023 Approved CHARLES BOGHOSKHAN
BUILDING-Rough-Frame 11/2/2023 Not Ready for Inspection STUART CHAPMAN
Final 11/2/2023 Corrections Issued STUART CHAPMAN
Green Building Final 11/2/2023 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 11/2/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 11/2/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/14/2023 Approved STUART CHAPMAN
Final 11/14/2023 Corrections Issued STUART CHAPMAN
Green Building Final 11/14/2023 Approved STUART CHAPMAN
Final 12/1/2023 No Access for Inspection RONNIE MINDANAO
ELECTRICAL-Final 8/19/2024 Approved STUART CHAPMAN
Final 8/19/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/19/2024 Approved STUART CHAPMAN
PLUMBING-Final 8/19/2024 Approved STUART CHAPMAN
Service/Power Release 8/19/2024 Approved STUART CHAPMAN