2708 S MENLO AVE 90007

Certificate Information: 2708 S MENLO AVE 90007

Application / Permit
21010-10000-05852
Plan Check / Job No.
B21LA21173
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN PROPOSED 2-STORY DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 6/13/2022
Issuing Office
Current Status
CofO Issued on 11/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 MICHAEL LOPEZ
Corrections Issued 12/2/2021 MICHAEL LOPEZ
Quality Review Completed 12/13/2021 HERNAN ARREOLA
Applicant returned to address corrections 2/25/2022 MICHAEL LOPEZ
Applicant returned to address corrections 3/9/2022 MICHAEL LOPEZ
Plan Check Approved 3/25/2022 MICHAEL LOPEZ
Issued 6/13/2022 APPLICANT
CofO in Progress 10/28/2023 ALIZAH MAYAGOITIA
Permit Finaled 11/5/2023 DEROLD HAUFF
CofO Issued 11/5/2023 DEROLD HAUFF
Permit Finaled 11/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/8/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/8/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 12/8/2021 CHRISTOPHER ROCHA
Low Impact Development Cleared 1/26/2022 SARAH YOUSSEF
Historic monument Cleared 1/27/2022 DANIEL MATA
Roof/Waste drainage to street Cleared 1/27/2022 CHRISTOPHER ROCHA
Specific Plan Cleared 1/27/2022 DANIEL MATA
City Hist. Cultural Monument Cleared 2/8/2022 DANIEL MATA
ZI Cleared 2/28/2022 JASON CHAN

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: NA35389       ,
Contractor J P Demo Inc; Lic. No.: 1001814-B       ,
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272
Geologist Kaligi,, Azad Adam; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/8/2022 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Barrier 7/8/2022 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 7/8/2022 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 7/15/2022 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 8/18/2022 Partial Approval KATHRYN BUTTERWORTH
Sewer 8/18/2022 Approved KATHRYN BUTTERWORTH
Underground Mechanical 8/18/2022 Corrections Issued KATHRYN BUTTERWORTH
Insulation 8/25/2022 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 8/30/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 8/30/2022 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 8/30/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 9/30/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 9/30/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 9/30/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/8/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 12/8/2022 Approved KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 12/8/2022 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 12/8/2022 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 12/27/2022 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 1/4/2023 Corrections Issued STUART CHAPMAN
Insulation 1/17/2023 Corrections Issued KATHRYN BUTTERWORTH
Shower Pan 1/17/2023 Approved KATHRYN BUTTERWORTH
Insulation 1/20/2023 No Access for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 1/23/2023 Approved KATHRYN BUTTERWORTH
Insulation 1/23/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 1/27/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 2/7/2023 Partial Approval KATHRYN BUTTERWORTH
Sewer 3/24/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 6/13/2023 Corrections Issued STUART CHAPMAN
Green Building Final 6/13/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 6/13/2023 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 6/13/2023 Approved STUART CHAPMAN
Final 6/23/2023 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 6/23/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 7/7/2023 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 7/7/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 10/16/2023 Approved KATHRYN BUTTERWORTH
Final 10/16/2023 Corrections Issued KATHRYN BUTTERWORTH
Gas Test 10/16/2023 Approved KATHRYN BUTTERWORTH
HVAC-Final 10/16/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 10/16/2023 Approved KATHRYN BUTTERWORTH
Service/Power Release 10/16/2023 Approved KATHRYN BUTTERWORTH
Final 10/27/2023 OK to Issue CofO ALIZAH MAYAGOITIA