2421 S PATRICIA AVE 90064

Certificate Information: 2421 S PATRICIA AVE 90064

Application / Permit
21010-10000-05850
Plan Check / Job No.
B21LA21171
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 4/14/2022
Issuing Office
Current Status
CofO Issued on 6/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 CARLOS MONTES
Corrections Issued 12/11/2021 CARLOS MONTES
Quality Review Completed 12/14/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/4/2022 CARLOS MONTES
Plan Check Approved 3/18/2022 CARLOS MONTES
Issued 4/14/2022 APPLICANT
Permit Finaled 6/24/2024 DANIEL ORRANTE
CofO Issued 6/24/2024 DANIEL ORRANTE
Permit Finaled 6/24/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 12/13/2021 ANTHONY VARGAS
Construction near power lines Cleared 12/27/2021 WALTER RAMIREZ
Address approval Cleared 12/28/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 12/28/2021 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 12/28/2021 DENNIS BRAGIN
Sewer availability Cleared 12/28/2021 HISASHI KOBAYAKAWA
Tenant Habitability Plan Cleared 12/28/2021 PHILLIP MUNGUIA
Grading Pre-Inspection Cleared 1/10/2022 ALEXANDER HELFER
Specific Plan Cleared 2/28/2022 VALERIA CEJA
GPI Written Notices Cleared 3/18/2022 ALEXANDER HELFER

Contact Information

Contractor Umholtz J R Framing; Lic. No.: 722480-B       ,
Engineer , ; Lic. No.: S3340       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/15/2022 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 6/15/2022 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 6/15/2022 Not Ready for Inspection KEVIN SARGSYAN
Deputy Methane Barrier 6/16/2022 No Access for Inspection MICHAEL PELHAM
Deputy Methane Barrier 6/17/2022 Approved MICHAEL PELHAM
Deputy Methane Barrier 6/21/2022 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 7/7/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/7/2022 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 7/7/2022 Approved KEVIN SARGSYAN
METHANE-Subgrade 7/7/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/11/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/18/2022 Partial Approval KEVIN SARGSYAN
Special/Order Compliance 7/20/2022 Partial Approval OGANES TARAKHCHYAN
Special/Order Compliance 7/25/2022 Approved PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 No Access for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/7/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/9/2022 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 9/9/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 9/27/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/7/2022 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/12/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/17/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 10/17/2022 Approved OGANES TARAKHCHYAN
Insulation 10/17/2022 Approved OGANES TARAKHCHYAN
METHANE-Final 10/17/2022 Approved OGANES TARAKHCHYAN
METHANE-Rough 10/17/2022 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 10/17/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 10/21/2022 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/31/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 11/3/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/18/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 11/22/2022 Approved ASHLEY THOMPSON
Sewer 4/19/2023 No Access for Inspection CLAYTON GRAHAM
Sewer 4/20/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 6/9/2023 Partial Approval CLAYTON GRAHAM
PLUMBING-Final 8/22/2023 Partial Inspection CLAYTON GRAHAM
PLUMBING-Rough 8/29/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 9/25/2023 Corrections Issued BEN MOLSTAD
Final 9/25/2023 Corrections Issued BEN MOLSTAD
HVAC-Final 9/25/2023 Corrections Issued BEN MOLSTAD
PLUMBING-Final 9/25/2023 Corrections Issued BEN MOLSTAD
Final 10/17/2023 Not Ready for Inspection CLAYTON GRAHAM
Footing/Foundation/Slab 10/17/2023 Approved CLAYTON GRAHAM
HVAC-Final 10/17/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 10/17/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Not Ready CLAYTON GRAHAM
Service/Power Release 10/17/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Final 1/24/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 1/30/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Not Required OGANES TARAKHCHYAN
Smoke Detectors 1/30/2024 Approved OGANES TARAKHCHYAN
Final 5/17/2024 Corrections Issued ASHLEY THOMPSON
Service/Power Release 5/17/2024 Not Ready for Inspection ASHLEY THOMPSON
Final 6/5/2024 Corrections Issued JESUS RODRIGUEZ
Final 6/21/2024 Conditional Approval ASHLEY THOMPSON