4246 S LYCEUM AVE 90066
Certificate Information: 4246 S LYCEUM AVE 90066
- Application / Permit
- 21010-10000-05847
- Plan Check / Job No.
- B21LA21158
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED GARAGE CONVERSION TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | JOE VO |
| Corrections Issued | 11/12/2021 | JOE VO |
| Plan Check Approved | 11/19/2021 | JOE VO |
| Issued | 12/8/2021 | APPLICANT |
| CofO in Progress | 4/20/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
| CofO Issued | 4/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 11/17/2021 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/31/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/21/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 12/29/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/29/2022 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 12/29/2022 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 1/17/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 1/23/2023 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 1/26/2023 | Approved | HERBERT GIRON |
| Insulation | 1/26/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 2/14/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 2/14/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/14/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 2/14/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| Final | 4/19/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/19/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/19/2023 | Approved | JESUS RODRIGUEZ |