4521 1/2 N MOSHER AVE 90031

Certificate Information: 4521 1/2 N MOSHER AVE 90031

Application / Permit
21010-10000-05831
Plan Check / Job No.
B21LA21107
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan PROPOSED 1 STORY DETACHED ADU
Permit Issued
Issued on 11/8/2022
Issuing Office
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 CRYSTEL MAALOUF
Corrections Issued 12/21/2021 CRYSTEL MAALOUF
Quality Review Completed 12/24/2021 PRANITA SHAH
Applicant returned to address corrections 8/5/2022 CRYSTEL MAALOUF
Plan Check Approved 8/29/2022 CRYSTEL MAALOUF
Issued 11/8/2022 APPLICANT
CofO in Progress 11/3/2025 CHARLES BOGHOSKHAN
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/10/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/14/2022 TREVOR QUAN
Sewer availability Cleared 2/14/2022 TREVOR QUAN
Hydrant and Access approval Cleared 4/11/2022 LAURINDA MEADE
Low Impact Development Cleared 5/19/2022 JORGE MEJIA LEMUS
CPC Cleared 5/26/2022 KATIE DEBIASE
HPOZ Cleared 5/26/2022 KATIE DEBIASE
Miscellaneous Cleared 5/26/2022 KATIE DEBIASE
Roof/Waste drainage to street Cleared 7/29/2022 AMAAN MALIK
GPI Written Notices Cleared 8/29/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 8/29/2022 CRYSTEL MAALOUF

Contact Information

Architect Vilppu,, Lydia Nadine; Lic. No.: C31349 3108 GLENDALE BLVD #512      LOS ANGELES, CA 90039
Architect Vilppu,, Lydia Nadine; Lic. No.: NA31349       ,
Contractor Livingprospex Corporation; Lic. No.: 1064984-B       ,
Engineer Youm,, Moung Han; Lic. No.: C74086 309 S BERENDO ST APT 6      LOS ANGELES, CA 90020

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/4/2023 Partial Inspection AMY COLIN
Footing/Foundation/Slab 4/14/2023 Corrections Issued AMY COLIN
PLUMBING-Rough 4/14/2023 Partial Approval AMY COLIN
Sewer 4/14/2023 Approved AMY COLIN
Footing/Foundation/Slab 5/5/2023 Approved AMY COLIN
Gas Test 5/5/2023 Partial Approval AMY COLIN
BUILDING-Rough-Frame 6/29/2023 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 6/29/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Not Ready for Inspection AMY COLIN
HVAC-Rough 6/29/2023 Approved AMY COLIN
MERV13>=Rough 6/29/2023 Approved AMY COLIN
PLUMBING-Rough 6/29/2023 Corrections Issued AMY COLIN
Verify Sprinkler Sign Off 6/29/2023 Approved AMY COLIN
Wood Frame 6/29/2023 Corrections Issued AMY COLIN
Wood Frame 7/10/2023 Approved AMY COLIN
Insulation 7/24/2023 Approved AMY COLIN
Interior/Exterior Lathing 7/24/2023 Approved AMY COLIN
Drywall Nailing 8/4/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Not Ready AMY COLIN
BUILDING-Rough-Frame 9/21/2023 Approved SCOTT FINNILA
Final 9/21/2023 Corrections Issued SCOTT FINNILA
MERV13>=Final 9/21/2023 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 9/21/2023 Approved SCOTT FINNILA
Smoke Detectors 9/21/2023 Approved SCOTT FINNILA
Final 5/14/2024 OK to Issue CofO BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 5/14/2024 SGSOV Approved BRENDAN MORELLI