4521 1/2 N MOSHER AVE 90031
Certificate Information: 4521 1/2 N MOSHER AVE 90031
- Application / Permit
- 21010-10000-05831
- Plan Check / Job No.
- B21LA21107
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED 1 STORY DETACHED ADU
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 12/21/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/24/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 8/5/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/29/2022 | CRYSTEL MAALOUF |
| Issued | 11/8/2022 | APPLICANT |
| CofO in Progress | 11/3/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 2/14/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 4/11/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 5/19/2022 | JORGE MEJIA LEMUS |
| CPC | Cleared | 5/26/2022 | KATIE DEBIASE |
| HPOZ | Cleared | 5/26/2022 | KATIE DEBIASE |
| Miscellaneous | Cleared | 5/26/2022 | KATIE DEBIASE |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | AMAAN MALIK |
| GPI Written Notices | Cleared | 8/29/2022 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 8/29/2022 | CRYSTEL MAALOUF |
Contact Information
| Architect | Vilppu,, Lydia Nadine; Lic. No.: C31349 | 3108 GLENDALE BLVD #512 LOS ANGELES, CA 90039 |
| Architect | Vilppu,, Lydia Nadine; Lic. No.: NA31349 | , |
| Contractor | Livingprospex Corporation; Lic. No.: 1064984-B | , |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2023 | Partial Inspection | AMY COLIN |
| Footing/Foundation/Slab | 4/14/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 4/14/2023 | Partial Approval | AMY COLIN |
| Sewer | 4/14/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 5/5/2023 | Approved | AMY COLIN |
| Gas Test | 5/5/2023 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 6/29/2023 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 6/29/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 6/29/2023 | Approved | AMY COLIN |
| MERV13>=Rough | 6/29/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 6/29/2023 | Corrections Issued | AMY COLIN |
| Verify Sprinkler Sign Off | 6/29/2023 | Approved | AMY COLIN |
| Wood Frame | 6/29/2023 | Corrections Issued | AMY COLIN |
| Wood Frame | 7/10/2023 | Approved | AMY COLIN |
| Insulation | 7/24/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 7/24/2023 | Approved | AMY COLIN |
| Drywall Nailing | 8/4/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Not Ready | AMY COLIN |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | SCOTT FINNILA |
| Final | 9/21/2023 | Corrections Issued | SCOTT FINNILA |
| MERV13>=Final | 9/21/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | SCOTT FINNILA |
| Service/Power Release | 9/21/2023 | Approved | SCOTT FINNILA |
| Smoke Detectors | 9/21/2023 | Approved | SCOTT FINNILA |
| Final | 5/14/2024 | OK to Issue CofO | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | BRENDAN MORELLI |