15531 W SUPERIOR ST 91343
Certificate Information: 15531 W SUPERIOR ST 91343
- Application / Permit
- 21010-10000-05830
- Plan Check / Job No.
- B21LA21102
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (2 OF 2) ONE STORY ADU 1200SF (40X 30 ) With Attached (N) Porch/Trellis Per LAMC 12.22 A.33(c),(d)
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | KHUONG TRUONG |
| Corrections Issued | 12/14/2021 | KHUONG TRUONG |
| Quality Review Completed | 12/23/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/27/2021 | APPLICANT |
| Applicant returned to address corrections | 8/4/2022 | KHUONG TRUONG |
| Plan Check Approved | 8/15/2022 | KHUONG TRUONG |
| Issued | 8/22/2022 | APPLICANT |
| CofO in Progress | 2/9/2024 | CHRISTOPHER ROJAS |
| CofO in Progress | 2/29/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/25/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/18/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/28/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 12/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/6/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Sewer | 2/6/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 2/6/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Wood Frame | 2/6/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 2/14/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/4/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 5/4/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 5/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/12/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/12/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 12/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| MERV13>=Final | 12/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 12/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 12/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 1/18/2024 | Corrections Issued | DAVID MATSON |
| Green Building Final | 1/18/2024 | Approved | DAVID MATSON |
| MERV13>=Final | 1/18/2024 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 1/18/2024 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 1/18/2024 | Approved | DAVID MATSON |
| Final | 1/26/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 1/26/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/7/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |