2342 1/2 S COCHRAN AVE 90016
Certificate Information: 2342 1/2 S COCHRAN AVE 90016
- Application / Permit
- 21010-10000-05825
- Plan Check / Job No.
- B21LA21043
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER 12.22 A 33 C & D
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | STARR CHEN |
| Corrections Issued | 12/5/2021 | STARR CHEN |
| Quality Review Completed | 12/14/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| Applicant returned to address corrections | 9/13/2022 | STARR CHEN |
| Plan Check Approved | 4/18/2023 | STARR CHEN |
| Issued | 4/19/2023 | APPLICANT |
| CofO in Progress | 12/1/2023 | JOSE AVILA |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | WALLIE JONG |
| Sewer availability | Cleared | 1/10/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 3/17/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/4/2023 | GILBERT URREA |
| Low Impact Development | Cleared | 4/11/2023 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/11/2023 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/8/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/18/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/18/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 6/21/2023 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 6/29/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 6/29/2023 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 6/29/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 6/29/2023 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 7/18/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 7/18/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/18/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/1/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 8/9/2023 | Approved | JOSE AVILA |
| Insulation | 8/9/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 8/18/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/18/2023 | Approved | JOSE AVILA |
| Sewer | 10/10/2023 | Corrections Issued | JOSE AVILA |
| Sewer | 10/13/2023 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 11/14/2023 | Approved | JOSE AVILA |
| HVAC-Final | 11/14/2023 | Corrections Issued | JOSE AVILA |
| MERV13>=Final | 11/14/2023 | Approved | JOSE AVILA |
| MERV13>=Rough | 11/14/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 11/14/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 11/14/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 11/14/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 11/14/2023 | Approved | JOSE AVILA |
| Final | 11/28/2023 | OK to Issue CofO | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Approved | JOSE AVILA |