2714 S PORTLAND ST 90007

Certificate Information: 2714 S PORTLAND ST 90007

Application / Permit
21010-10000-05817
Plan Check / Job No.
B21LA21016
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(7) Carport
Work Description
NEW DETACHED CARPORT WITH STORAGE ROOMS. Building to be fully equipped an automatic sprinkler sys in accordance with NFPA 13
Permit Issued
Issued on 6/9/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 MONICA RAMIREZ
Disabled Access Plans Picked Up 11/22/2021 APPLICANT
Corrections Issued 11/30/2021 MONICA RAMIREZ
Quality Review Completed 12/10/2021 KEN GILL
Applicant returned to address corrections 1/25/2022 MONICA RAMIREZ
Applicant returned to address corrections 3/7/2022 MONICA RAMIREZ
Applicant returned to address corrections 5/17/2022 MONICA RAMIREZ
Plan Check Approved 5/19/2022 MONICA RAMIREZ
Issued 6/9/2022 APPLICANT
CofO in Progress 3/24/2023 JAMES POWERS
Permit Finaled 3/24/2023 ERNESTO CORRAL
CofO Issued 3/24/2023 ERNESTO CORRAL
Permit Finaled 3/24/2023 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 12/13/2021 MAX LODER
Redevelopment Project Area Cleared 12/14/2021 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 12/16/2021 JEANIE LAM
Low Impact Development Cleared 1/21/2022 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 1/21/2022 JEANIE LAM
Hydrant and Access approval Cleared 2/18/2022 DWAYNE LAURENT
DAS Clearance Cleared 3/10/2022 SHINE LIN

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 1810 14TH STREET SUITE 204      SANTA MONICA, CA 90404
Contractor C T C Renovation Inc; Lic. No.: 1007234-B 21356 NORDHOFF STREET #107      CHATSWORTH, CA 91311
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272
Geologist Kaligi,, Azad Adam; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 9/23/2022 Partial Approval JAMES POWERS
METHANE-Subgrade 9/23/2022 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/26/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Not Ready for Inspection JAMES POWERS
Green Building Rough 11/21/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 11/21/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 11/21/2022 Not Ready for Inspection JAMES POWERS
Green Building Rough 12/6/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 12/6/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 12/6/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 12/9/2022 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 12/9/2022 Not Ready for Inspection ALAN MORELOS
METHANE-Rough 12/9/2022 Not Ready for Inspection ALAN MORELOS
Wood Frame 12/9/2022 Not Ready for Inspection ALAN MORELOS
Drywall Nailing 1/13/2023 Partial Approval GREGORY POMISH
Final 2/3/2023 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 2/3/2023 Not Ready for Inspection GREGORY POMISH
Green Building Final 2/3/2023 Not Ready for Inspection GREGORY POMISH
Green Building Rough 2/3/2023 Not Ready for Inspection GREGORY POMISH
METHANE-Barrier 2/3/2023 Not Ready for Inspection GREGORY POMISH
METHANE-Final 2/3/2023 Not Ready for Inspection GREGORY POMISH
METHANE-Rough 2/3/2023 Not Ready for Inspection GREGORY POMISH
METHANE-Subgrade 2/3/2023 Not Ready for Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 2/3/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 2/3/2023 Not Ready for Inspection GREGORY POMISH
Green Building Rough 2/22/2023 Approved JAMES POWERS
Interior/Exterior Lathing 2/22/2023 Approved JAMES POWERS
METHANE-Rough 2/22/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 2/22/2023 Partial Approval JAMES POWERS
METHANE-Rough 3/2/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 3/2/2023 Not Ready for Inspection JAMES POWERS
Final 3/17/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 3/17/2023 Partial Approval JAMES POWERS
Green Building Final 3/17/2023 Approved JAMES POWERS
METHANE-Barrier 3/17/2023 Not Ready for Inspection JAMES POWERS
METHANE-Final 3/17/2023 Not Ready for Inspection JAMES POWERS
METHANE-Rough 3/17/2023 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 3/17/2023 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV No Gas JAMES POWERS
Smoke Detectors 3/17/2023 Approved JAMES POWERS
Wood Frame 3/17/2023 Partial Approval JAMES POWERS
Final 3/22/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 3/22/2023 Approved JAMES POWERS
METHANE-Barrier 3/22/2023 Approved JAMES POWERS
METHANE-Final 3/22/2023 Approved JAMES POWERS
METHANE-Rough 3/22/2023 Approved JAMES POWERS
METHANE-Subgrade 3/22/2023 Approved JAMES POWERS
Wood Frame 3/22/2023 Approved JAMES POWERS
Final 3/24/2023 OK to Issue CofO JAMES POWERS