1267-1267 1/2 E ADAMS BLVD 90011
Certificate Information: 1267-1267 1/2 E ADAMS BLVD 90011
- Application / Permit
- 21010-10000-05808
- Plan Check / Job No.
- B21LA20988
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH ATTACHED GARAGE (FRONT)
- Permit Issued
- Issued on 8/23/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | STARR CHEN |
| Corrections Issued | 1/7/2022 | STARR CHEN |
| Quality Review Completed | 1/11/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| Plan Check Approved | 5/25/2022 | STARR CHEN |
| Issued | 8/23/2023 | APPLICANT |
| CofO in Progress | 7/11/2024 | ALEJANDRO DE ARTOLA |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/18/2022 | RUBEN VASQUEZ |
| Address approval | Cleared | 1/25/2022 | CINDY QI |
| Frnt yard landscape/Water mgmt | Cleared | 1/27/2022 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | CINDY QI |
| Sewer availability | Cleared | 1/31/2022 | CINDY QI |
| Highway dedication | Cleared | 2/24/2022 | CINDY QI |
| Permit | Cleared | 2/24/2022 | CINDY QI |
| Trees in Parkway | Cleared | 3/18/2022 | STARR CHEN |
| Hydrant and Access approval | Cleared | 3/29/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/12/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/16/2022 | CINDY QI |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | PO BOX 39459 DOWNEY, CA 90241 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 10/5/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/5/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 1/11/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 1/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 5/13/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/14/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 6/14/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 6/14/2024 | Approved | JOSEPH MCGARRY |
| Verify Rec and Parks Fee Memo | 6/14/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 6/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/10/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/10/2024 | Approved | ALEJANDRO DE ARTOLA |