12836 W GILMORE AVE 90066
Certificate Information: 12836 W GILMORE AVE 90066
- Application / Permit
- 21010-10000-05784
- Plan Check / Job No.
- B21LA20876
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 2 STORY SINGLE FAMILY HOME W/ ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | CARLOS MONTES |
| Corrections Issued | 12/9/2021 | CARLOS MONTES |
| Quality Review Completed | 12/14/2021 | WING SUEN |
| Plan Check Approved | 2/11/2022 | CARLOS MONTES |
| Issued | 3/9/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 12/8/2022 | HERBERT GIRON |
| Permit Finaled | 12/17/2022 | DANIEL ORRANTE |
| CofO Issued | 12/17/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/17/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/21/2021 | FREDDY GARCIA |
| Low Impact Development | Cleared | 1/21/2022 | TA ANH |
| Address approval | Cleared | 1/27/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 1/27/2022 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 1/28/2022 | RAYMOND MUGAMBWA |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2022 | STEVEN JIN |
| Sewer availability | Cleared | 1/29/2022 | STEVEN JIN |
| Hydrant and Access approval | Cleared | 2/4/2022 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Partial Approval | DAVID FEILER |
| Sewer | 3/17/2022 | Approved | DAVID FEILER |
| Underground Mechanical | 3/17/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 3/31/2022 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/17/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/5/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 7/5/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/5/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 7/5/2022 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/5/2022 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 7/6/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 7/19/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 7/25/2022 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/29/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 7/29/2022 | Approved | HERBERT GIRON |
| Insulation | 7/29/2022 | Corrections Issued | HERBERT GIRON |
| Insulation | 8/3/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/11/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/11/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/17/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | HERBERT GIRON |
| METHANE-Rough | 10/17/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/21/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 11/21/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 11/21/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 11/21/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/21/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 11/30/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/30/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/2/2022 | Conditional Approval | HERBERT GIRON |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 12/7/2022 | Approved | HERBERT GIRON |
| Final | 12/7/2022 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 12/7/2022 | Approved | HERBERT GIRON |
| Service/Power Release | 12/7/2022 | Approved | HERBERT GIRON |