5005-5007 W 12TH ST 90019

Certificate Information: 5005-5007 W 12TH ST 90019

Application / Permit
21010-10000-05775
Plan Check / Job No.
B21LA20840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (E) GARAGE TO BE CONVERTED TO 2 ADUS WITH ADDITON
Permit Issued
Issued on 7/28/2022
Issuing Office
Current Status
CofO Issued on 1/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 CRYSTEL MAALOUF
Corrections Issued 11/30/2021 CRYSTEL MAALOUF
Quality Review Completed 12/5/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/12/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 3/1/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 6/22/2022 CRYSTEL MAALOUF
Plan Check Approved 7/27/2022 CRYSTEL MAALOUF
Issued 7/28/2022 APPLICANT
CofO in Progress 1/19/2024 RICHARD DOCKUS
Permit Finaled 1/28/2024 DEROLD HAUFF
CofO Issued 1/28/2024 DEROLD HAUFF
Permit Finaled 1/28/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/27/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/29/2021 JEANETTE VONG
Sewer availability Cleared 12/29/2021 JEANETTE VONG
CPC Cleared 12/30/2021 ANACANY HURTADO
Low Impact Development Cleared 2/4/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 2/10/2022 JEANETTE VONG
Construction near power lines Cleared 2/17/2022 RIDWAN HARDY
Construction within easement Cleared 2/17/2022 RIDWAN HARDY
Miscellaneous Cleared 6/16/2022 DALIA MOKAYED

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/20/2022 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 11/14/2022 Corrections Issued JULIAN AMAYA
Underground Mechanical 11/14/2022 Not Ready for Inspection JULIAN AMAYA
Deputy Methane Barrier 11/22/2022 Conditional Approval RICHARD DOCKUS
Deputy Methane Barrier 11/23/2022 Conditional Approval RICHARD DOCKUS
METHANE-Subgrade 11/29/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 11/29/2022 Corrections Issued RICHARD DOCKUS
Deputy Methane Barrier 12/19/2022 Conditional Approval RICHARD DOCKUS
Deputy Methane Barrier 12/21/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 1/11/2023 Partial Approval RICHARD DOCKUS
Green Building Rough 1/11/2023 Not Ready for Inspection RICHARD DOCKUS
METHANE-Rough 1/11/2023 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 3/7/2023 Approved RICHARD DOCKUS
ELECTRICAL-Rough 3/17/2023 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Corrections Issued RICHARD DOCKUS
HVAC-Rough 3/17/2023 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 4/6/2023 Approved RICHARD DOCKUS
Green Building Rough 4/6/2023 Approved RICHARD DOCKUS
HVAC-Rough 4/6/2023 Approved RICHARD DOCKUS
METHANE-Rough 4/6/2023 Approved RICHARD DOCKUS
Insulation 4/24/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/24/2023 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 4/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Methane Barrier 4/26/2023 Approved MICHAEL LEWIS
Drywall Nailing 5/3/2023 Approved RICHARD DOCKUS
Deputy Methane Barrier 5/9/2023 Conditional Approval RICHARD DOCKUS
Interior/Exterior Lathing 5/23/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 6/23/2023 Corrections Issued RICHARD DOCKUS
Underground Mechanical 7/25/2023 Partial Approval SCOTT FINNILA
Underground Mechanical 8/1/2023 Partial Approval LILIANA PORTILLO
Sewer 8/10/2023 Partial Approval LILIANA PORTILLO
Sewer 8/28/2023 Approved ROY SPAULDING
ELECTRICAL-Final 11/6/2023 Approved RICHARD DOCKUS
PLUMBING-Final 11/6/2023 Approved RICHARD DOCKUS
Final 1/3/2024 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/3/2024 Approved JOAQUIN GREENOUGH
Green Building Final 1/3/2024 Approved JOAQUIN GREENOUGH
HVAC-Final 1/3/2024 Corrections Issued JOAQUIN GREENOUGH
METHANE-Barrier 1/3/2024 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 1/3/2024 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 1/3/2024 Approved JOAQUIN GREENOUGH
Final 1/11/2024 OK to Issue CofO RICHARD DOCKUS
HVAC-Final 1/11/2024 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 1/11/2024 SGSOV Approved RICHARD DOCKUS