1432 E 49TH ST 90011
Certificate Information: 1432 E 49TH ST 90011
- Application / Permit
- 21010-10000-05773
- Plan Check / Job No.
- B21LA20813
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 1-STORY 2-CAR GARAGE AT REAR OF LOT
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/13/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/30/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/28/2022 | LUKE GONZALES |
| Applicant returned to address corrections | 3/26/2022 | AUNG SOE |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Plan Check Approved | 5/27/2022 | RICARDO RAMIREZ |
| Issued | 6/3/2022 | APPLICANT |
| CofO in Progress | 12/13/2023 | ALEJANDRO DE ARTOLA |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/4/2022 | TINA MIRANDA |
| Roof/Waste drainage to street | Cleared | 5/14/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | JEANETTE VONG |
Contact Information
| Contractor | Randle Construction; Lic. No.: 1002172-B | 13838 ROPER AVENUE NORWALK, CA 90650 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/27/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/28/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/28/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/17/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 11/17/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | JULIAN AMAYA |
| ELECTRICAL-Rough | 12/8/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/9/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/9/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 2/9/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 3/6/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 3/17/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 4/26/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/12/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/12/2023 | Approved | ALEJANDRO DE ARTOLA |