10400 N JOHANNA AVE 91040

Certificate Information: 10400 N JOHANNA AVE 91040

Application / Permit
21010-10000-05751
Plan Check / Job No.
B21LA20748
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 1-story Type V-A single family dwelling with NFPA-13R. Per engineer details.
Permit Issued
Issued on 8/26/2025
Issuing Office
Metro
Current Status
Issued on 8/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 GARO TELMI
Corrections Issued 12/10/2021 GARO TELMI
Quality Review Completed 12/16/2021 KEN GILL
Building Plans Picked Up 12/21/2021 APPLICANT
Applicant returned to address corrections 1/27/2022 GARO TELMI
Applicant returned to address corrections 6/16/2022 GARO TELMI
Applicant returned to address corrections 7/7/2022 GARO TELMI
Applicant returned to address corrections 3/20/2024 GARO TELMI
Applicant returned to address corrections 8/27/2024 GARO TELMI
Plan Check Approved 12/19/2024 VICTOR CHEN
No Progress 12/19/2024 VICTOR CHEN
Plan Check Approved 4/10/2025 VICTOR CHEN
Issued 8/26/2025 APPLICANT

Permit Application Clearance Information

Disturb/Remove Protected Trees Cleared 5/6/2022 ADALBERTO VERA
Trees in Parkway Cleared 5/19/2022 ADALBERTO VERA
Address approval Cleared 5/27/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 5/27/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 5/27/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 5/27/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 5/27/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 5/27/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/27/2022 ROMAN GUTIERREZ
Permit Cleared 5/27/2022 ROMAN GUTIERREZ
Drainage to Storm Drain Cleared 6/14/2022 CARLOS AGUILERA
Sewer availability Cleared 6/14/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 6/16/2022 MATTHEW CRAIG
Miscellaneous Cleared 11/3/2022 DANIEL CORONADO
BHO/Hillside ordinance Cleared 4/26/2024 JOHN LIN
BHO/Hillside ordinance Cleared 4/26/2024 JOHN LIN
BHO/Hillside ordinance Cleared 4/26/2024 JOHN LIN
BHO/Hillside ordinance Cleared 4/26/2024 JOHN LIN
BHO/Hillside ordinance Cleared 4/26/2024 JOHN LIN
Permit Cleared 4/26/2024 JOHN LIN
Sewer availability Cleared 4/26/2024 JOHN LIN
Low Impact Development Cleared 5/26/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/29/2024 JOHN LIN
Miscellaneous Cleared 8/30/2024 DORIAN AGUILAR
Specific Plan Cleared 8/30/2024 DORIAN AGUILAR
Grading Pre-Inspection Cleared 12/17/2024 GARO TELMI

Contact Information

Contractor Owner-Builder       ,
Engineer Abedian,, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504
Engineer Samiee,, Mohammad Esmail; Lic. No.: C46172 PO BOX 834      SAN DIMAS, CA 91773

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/18/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 2/9/2026 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 2/9/2026 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 2/9/2026 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 2/12/2026 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 2/12/2026 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 2/24/2026 Approved MATTHEW NELSON
Footing/Foundation/Slab 2/24/2026 Approved MATTHEW NELSON
PLUMBING-Rough 4/17/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/20/2026 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 5/11/2026 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/11/2026 Approved DAVID ANDERSON
Green Building Rough 5/11/2026 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 5/11/2026 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 6/8/2026 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 6/8/2026 Corrections Issued DAVID ANDERSON
Green Building Rough 6/8/2026 Approved DAVID ANDERSON
HVAC-Rough 6/8/2026 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 6/8/2026 Approved DAVID ANDERSON
Wood Frame 6/8/2026 Not Ready for Inspection DAVID ANDERSON
Interior/Exterior Lathing 6/9/2026 Partial Approval DAVID ANDERSON
Insulation 6/11/2026 Corrections Issued DAVID ANDERSON
Drywall Nailing 6/18/2026 Approved DAVID ANDERSON
Insulation 6/18/2026 Approved DAVID ANDERSON