745 N CAHUENGA BLVD 90038

Certificate Information: 745 N CAHUENGA BLVD 90038

Application / Permit
21010-10000-05748
Plan Check / Job No.
B21LA20733
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(7) Garage parking
Work Description
NEW FOUR TIER PARKING STRUCTURE
Permit Issued
Issued on 4/12/2023
Issuing Office
Metro
Current Status
Issued on 4/12/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 FARSHAD ALIMOHAMADI
Disabled Access Plans Picked Up 12/13/2021 APPLICANT
Corrections Issued 12/15/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 12/16/2021 SAI KHUM
Building Plans Picked Up 12/20/2021 APPLICANT
Green Plans Picked Up 12/28/2021 APPLICANT
Applicant returned to address corrections 1/6/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/8/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/26/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/3/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/4/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/30/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/4/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/11/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 4/12/2023 FARSHAD ALIMOHAMADI
Issued 4/12/2023 APPLICANT

Permit Application Clearance Information

ZI Cleared 12/27/2021 LOUIS ORTEGA
Address approval Cleared 1/4/2022 KHOUNG LE
Sewer availability Cleared 1/4/2022 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 1/26/2022 KHOUNG LE
Hydrant and Access approval Cleared 3/25/2022 MATTHEW CRAIG
Driveway location Cleared 3/29/2022 KEVIN ARUCAN
Internal circulation Cleared 3/29/2022 KEVIN ARUCAN
Trees in Parkway Cleared 5/4/2022 ADALBERTO VERA
Green Code Cleared 5/16/2022 FARSHAD ALIMOHAMADI
Prkng lot landscape/Water mgmt Cleared 5/24/2022 LOUIS ORTEGA
Building over 36-ft Cleared 6/1/2022 CALOSHA APPROVED
Highway dedication Cleared 6/7/2022 JEANETTE VONG
Miscellaneous Cleared 8/2/2022 MARITZA PRZEKOP
Construction near power lines Cleared 9/22/2022 RIDWAN HARDY
Permit Cleared 9/26/2022 MATIAS FARFAN
Encroachment in public way Cleared 9/28/2022 JEREMY CHOK
Low Impact Development Cleared 10/21/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/27/2022 BIJAN ZADEH
DAS Clearance Cleared 11/2/2022 SHINE LIN
Work Adjacent to Public Way Cleared 4/6/2023 LARRY LEE

Contact Information

Architect Cataldo,, John G; Lic. No.: C10457 835 MISSION STREET      SOUTH PASADENA, CA 91030
Contractor West Hills Construction Inc; Lic. No.: 578578-B 423 JENKS CIRCLE STE 101      CORONA, CA 92880
Engineer Morton,, Kevin Gerald; Lic. No.: S5181 446 MISSOURI ST      SAN FRANCISCO, CA 94107

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/11/2023 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 5/11/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Barrier 5/11/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Subgrade 5/11/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 5/16/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/16/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 5/16/2023 Partial Inspection EDWIN GREGORYONA
METHANE-Subgrade 5/16/2023 Partial Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/17/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 5/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/24/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/24/2023 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 5/24/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Barrier 5/24/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Subgrade 5/24/2023 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/25/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/1/2023 Partial Approval GREGORY POMISH
Green Building Rough 6/1/2023 Not Ready for Inspection GREGORY POMISH
METHANE-Rough 6/1/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Masonry Frame 6/1/2023 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/6/2023 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/13/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 6/16/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/21/2023 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/23/2023 Conditional Approval DARRYL ARNOLD
METHANE-Subgrade 7/17/2023 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 7/28/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Barrier 7/28/2023 Partial Inspection DAVID BURKHEAD
METHANE-Subgrade 7/28/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/29/2023 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/7/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/7/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 8/7/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Pre-Stress Concrete 8/16/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 8/17/2023 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 8/21/2023 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 8/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Pre-Stress Concrete 8/23/2023 Approved DAVID BURKHEAD
Footing/Foundation/Slab 8/23/2023 Partial Approval DAVID BURKHEAD
METHANE-Barrier 8/23/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Pre-Stress Concrete 8/24/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 8/25/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 8/28/2023 Approved TIMOTHY POWELL
Reinforced Concrete Frame 8/28/2023 Partial Approval TIMOTHY POWELL
Deputy Reinf. Concrete 8/30/2023 Conditional Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 8/30/2023 Partial Approval TIMOTHY POWELL
Deputy Pre-Stress Concrete 8/31/2023 No Access for Inspection TIMOTHY POWELL
Deputy Reinf. Concrete 9/6/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 9/7/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/7/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/12/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/12/2023 Partial Approval TIMOTHY POWELL
Deputy Reinf. Concrete 9/13/2023 Conditional Approval DAVID BURKHEAD
Deputy Other (see comments) 9/18/2023 Approved TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 9/18/2023 Partial Approval TIMOTHY POWELL
Deputy Reinf. Concrete 9/19/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 9/20/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 9/21/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 9/26/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 9/27/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/27/2023 Partial Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 9/29/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 10/3/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 10/4/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/5/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/5/2023 Partial Approval LARRY ARNICK
Deputy Pre-Stress Concrete 10/6/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/12/2023 Conditional Approval LARRY ARNICK
Deputy Pre-Stress Concrete 10/16/2023 Conditional Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 10/17/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/17/2023 Partial Approval DAVID BURKHEAD
Deputy Pre-Stress Concrete 10/18/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/18/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/20/2023 Partial Approval EDWIN GREGORYONA
Deputy Pre-Stress Concrete 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Pre-Stress Concrete 10/24/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/24/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 10/26/2023 Conditional Approval DAVID BURKHEAD
Green Building Rough 10/26/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 10/26/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 10/26/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 10/27/2023 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 10/27/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/30/2023 Partial Approval EDWIN GREGORYONA
Deputy Pre-Stress Concrete 10/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 11/3/2023 Partial Approval EDWIN GREGORYONA
Deputy Pre-Stress Concrete 11/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Pre-Stress Concrete 11/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Pre-Stress Concrete 11/9/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/9/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/15/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/15/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/16/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 11/17/2023 Partial Approval EDWIN GREGORYONA
Deputy Pre-Stress Concrete 11/29/2023 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/29/2023 Partial Approval RAFAEL ESPINOZA
Deputy Pre-Stress Concrete 11/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Pre-Stress Concrete 12/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/6/2023 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 12/6/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 12/8/2023 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 12/8/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/12/2023 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 12/12/2023 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 12/14/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 12/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/18/2023 Conditional Approval RONALD JIMENEZ
Deputy Reinf. Masonry 12/18/2023 Conditional Approval RONALD JIMENEZ
Masonry Wall/Backfill 12/18/2023 Partial Approval RONALD JIMENEZ
Deputy Steel/Welding 12/21/2023 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 12/21/2023 Partial Approval GREGORY POMISH
Deputy Steel/Welding 12/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/2/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/4/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/5/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/21/2024 Conditional Approval MICHAEL ROSENBERG
Special/Order Compliance 2/29/2024 Approved DAVID BURKHEAD
Special/Order Compliance 3/27/2024 Approved DAVID BURKHEAD
Special/Order Compliance 3/29/2024 Approved DAVID BURKHEAD
Final 4/1/2024 Corrections Issued DAVID BURKHEAD
Footing/Foundation/Slab 4/1/2024 Approved DAVID BURKHEAD
Green Building Final 4/1/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 4/1/2024 Approved DAVID BURKHEAD
METHANE-Barrier 4/1/2024 Approved DAVID BURKHEAD
METHANE-Final 4/1/2024 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 4/1/2024 Approved DAVID BURKHEAD
Reinforced Masonry Frame 4/1/2024 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV No Gas DAVID BURKHEAD
Smoke Detectors 4/1/2024 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 6/17/2024 Approved DAVID BURKHEAD