143-145 E 105TH ST 90003
Certificate Information: 143-145 E 105TH ST 90003
- Application / Permit
- 21010-10000-05730
- Plan Check / Job No.
- B21LA20647
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 1-CAR GARRAGE AT FRONT AND 2-CAR GARAGE AT REAR
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | ALBERT SERVIN |
| Corrections Issued | 12/3/2021 | ALBERT SERVIN |
| Quality Review Completed | 12/8/2021 | PETER KIM |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Applicant returned to address corrections | 1/6/2022 | ALBERT SERVIN |
| Plan Check Approved | 1/11/2022 | ALBERT SERVIN |
| Issued | 6/21/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | JOHN KLARIN |
| Permit Finaled | 2/23/2023 | ANSON MAGLASANG |
| CofO Issued | 2/23/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/23/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2021 | CINDY QI |
| Highway dedication | Cleared | 12/17/2021 | CINDY QI |
| Permit | Cleared | 12/17/2021 | CINDY QI |
| Hydrant and Access approval | Cleared | 12/18/2021 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | CINDY QI |
| Low Impact Development | Cleared | 12/23/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 12/27/2021 | CELINA MORENO |
| Sewer availability | Cleared | 12/28/2021 | JEANIE LAM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/5/2022 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 7/5/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/27/2022 | Approved | JOHN KLARIN |
| Sewer | 7/27/2022 | Approved | JOHN KLARIN |
| Underground Mechanical | 7/27/2022 | Approved | JOHN KLARIN |
| Wood Frame | 7/27/2022 | Partial Approval | JOHN KLARIN |
| Insulation | 7/28/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/17/2022 | Partial Approval | JOHN KLARIN |
| PLUMBING-Rough | 10/17/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/18/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/18/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/18/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 10/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/24/2022 | Approved | JOHN KLARIN |
| Insulation | 10/24/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/1/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/17/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 1/11/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 2/6/2023 | Approved | JOHN KLARIN |
| Final | 2/6/2023 | Corrections Issued | JOHN KLARIN |
| Gas Test | 2/6/2023 | Approved | JOHN KLARIN |
| Green Building Final | 2/6/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 2/6/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 2/6/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 2/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 2/6/2023 | Approved | JOHN KLARIN |
| Final | 2/15/2023 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 2/15/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 2/17/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 2/17/2023 | Approved | JOHN KLARIN |
| Final | 2/22/2023 | OK to Issue CofO | JOHN KLARIN |