926-928 E 79TH ST 90001
Certificate Information: 926-928 E 79TH ST 90001
- Application / Permit
- 21010-10000-05723
- Plan Check / Job No.
- B21LA20624
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | ALBERT SERVIN |
| Corrections Issued | 12/3/2021 | ALBERT SERVIN |
| Quality Review Completed | 12/8/2021 | PETER KIM |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Applicant returned to address corrections | 1/6/2022 | ALBERT SERVIN |
| Plan Check Approved | 1/11/2022 | ALBERT SERVIN |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 12/20/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
| CofO Issued | 12/31/2022 | DEROLD HAUFF |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/10/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | CELINA MORENO |
| Address approval | Cleared | 12/17/2021 | CHRISTOPHER ROCHA |
| Highway dedication | Cleared | 12/17/2021 | CHRISTOPHER ROCHA |
| Permit | Cleared | 12/17/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 12/20/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 12/20/2021 | CHRISTOPHER ROCHA |
| Frnt yard landscape/Water mgmt | Cleared | 12/27/2021 | KENTON TRINH |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/23/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/9/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 6/9/2022 | Partial Approval | LILIANA PORTILLO |
| Sewer | 6/9/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 6/9/2022 | Approved | LILIANA PORTILLO |
| Insulation | 6/10/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 7/7/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2022 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 7/28/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/28/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/2/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/2/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/2/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/9/2022 | Approved | LILIANA PORTILLO |
| Insulation | 8/9/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/16/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/16/2022 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 11/17/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/19/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/28/2022 | Approved | ALEJANDRO DE ARTOLA |