7733 S BOEING AVE 90045
Certificate Information: 7733 S BOEING AVE 90045
- Application / Permit
- 21010-10000-05687
- Plan Check / Job No.
- B21LA20474
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY ACCESSORY DWELLING UNIT PER STATE LAW AT REAR OF LOT.
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 8/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/6/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 12/1/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 12/5/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 12/17/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 1/14/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 3/13/2022 | FARSHAD ALIMOHAMADI |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| CofO in Progress | 8/12/2022 | BOBBY KEY |
| Permit Finaled | 8/22/2022 | DANIEL ORRANTE |
| CofO Issued | 8/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/19/2021 | JONATHAN HOM |
| Address approval | Cleared | 11/17/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 11/17/2021 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 11/23/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 11/23/2021 | SAUL GARCIA |
| Construction near power lines | Cleared | 3/8/2022 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 4/4/2022 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 4/5/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/28/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/28/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/28/2022 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 4/28/2022 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 4/28/2022 | Approved | BOBBY KEY |
| Insulation | 5/2/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 5/5/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/18/2022 | Corrections Issued | BOBBY KEY |
| Shower Pan | 5/18/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 5/23/2022 | Approved | BOBBY KEY |
| Shower Pan | 5/23/2022 | Approved | BOBBY KEY |
| Sewer | 6/13/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 6/13/2022 | Approved | BOBBY KEY |
| Gas Test | 6/17/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 7/1/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 7/1/2022 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 7/1/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 7/1/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 7/1/2022 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Not Ready | STEPHANIE SWANSON |
| Service/Power Release | 7/1/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 7/1/2022 | Approved | STEPHANIE SWANSON |
| Final | 7/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/25/2022 | Approved | RICHARD STEINBACH |
| Service/Power Release | 7/25/2022 | Approved | RICHARD STEINBACH |
| Final | 8/4/2022 | Conditional Approval | BOBBY KEY |
| PLUMBING-Final | 8/4/2022 | Approved | BOBBY KEY |
| Final | 8/12/2022 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/12/2022 | Approved | BOBBY KEY |