1917 S PALM GROVE AVE 90016
Certificate Information: 1917 S PALM GROVE AVE 90016
- Application / Permit
- 21010-10000-05651
- Plan Check / Job No.
- B21LA20297
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SINGLE FAMILY DWELLING WITH 2-CAR GARAGE
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | DANIEL YIP |
| Corrections Issued | 11/23/2021 | DANIEL YIP |
| Quality Review Completed | 11/30/2021 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 3/24/2022 | DANIEL YIP |
| Issued | 5/6/2022 | APPLICANT |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| CofO in Progress | 1/27/2023 | CALEB MEISTER |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
| CofO Issued | 2/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 12/27/2021 | JEANETTE VONG |
| Low Impact Development | Cleared | 1/7/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 1/7/2022 | JEANETTE VONG |
| Frnt yard landscape/Water mgmt | Cleared | 1/13/2022 | RUBEN VASQUEZ |
| Tenant Habitability Plan | Cleared | 2/3/2022 | MICHAEL SOTO |
| Hydrant and Access approval | Cleared | 3/9/2022 | MATTHEW CRAIG |
| Hold | Cleared | 5/16/2022 | JASON SHEETS |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-A | 3627 E FIRST STREET LOS ANGELES, CA 90063 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/11/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/24/2022 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/24/2022 | Approved | SCOTT FINNILA |
| Underground Mechanical | 6/1/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 7/8/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/26/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 7/26/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/26/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/26/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 7/26/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 7/26/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 7/26/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 7/27/2022 | Corrections Issued | STUART CHAPMAN |
| Insulation | 8/1/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/10/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/10/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/10/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 1/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 1/26/2023 | Approved | CALEB MEISTER |
| Final | 1/26/2023 | OK to Issue CofO | CALEB MEISTER |
| Green Building Final | 1/26/2023 | Approved | CALEB MEISTER |
| HVAC-Final | 1/26/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 1/26/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 1/26/2023 | Approved | CALEB MEISTER |
| Smoke Detectors | 1/26/2023 | Approved | CALEB MEISTER |