1917 S PALM GROVE AVE 90016

Certificate Information: 1917 S PALM GROVE AVE 90016

Application / Permit
21010-10000-05651
Plan Check / Job No.
B21LA20297
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SINGLE FAMILY DWELLING WITH 2-CAR GARAGE
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 DANIEL YIP
Corrections Issued 11/23/2021 DANIEL YIP
Quality Review Completed 11/30/2021 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 3/24/2022 DANIEL YIP
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/10/2022 APPLICANT
CofO in Progress 1/27/2023 CALEB MEISTER
Permit Finaled 2/14/2023 DEROLD HAUFF
Permit Finaled 2/14/2023 DEROLD HAUFF
CofO Issued 2/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/27/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/27/2021 JEANETTE VONG
Sewer availability Cleared 12/27/2021 JEANETTE VONG
Low Impact Development Cleared 1/7/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 1/7/2022 JEANETTE VONG
Frnt yard landscape/Water mgmt Cleared 1/13/2022 RUBEN VASQUEZ
Tenant Habitability Plan Cleared 2/3/2022 MICHAEL SOTO
Hydrant and Access approval Cleared 3/9/2022 MATTHEW CRAIG
Hold Cleared 5/16/2022 JASON SHEETS

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-A 3627 E FIRST STREET      LOS ANGELES, CA 90063

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/11/2022 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/24/2022 Approved SCOTT FINNILA
Footing/Foundation/Slab 5/24/2022 Approved SCOTT FINNILA
Underground Mechanical 6/1/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 7/8/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/26/2022 Partial Approval STUART CHAPMAN
Deputy Wood Construction 7/26/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/26/2022 Approved STUART CHAPMAN
Green Building Rough 7/26/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 7/26/2022 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 7/26/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 7/26/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 7/27/2022 Corrections Issued STUART CHAPMAN
Insulation 8/1/2022 Approved STUART CHAPMAN
Drywall Nailing 8/10/2022 Approved STUART CHAPMAN
Green Building Rough 8/10/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/10/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/19/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/26/2023 Approved CALEB MEISTER
ELECTRICAL-Final 1/26/2023 Approved CALEB MEISTER
Final 1/26/2023 OK to Issue CofO CALEB MEISTER
Green Building Final 1/26/2023 Approved CALEB MEISTER
HVAC-Final 1/26/2023 Approved CALEB MEISTER
PLUMBING-Final 1/26/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Approved CALEB MEISTER
Service/Power Release 1/26/2023 Approved CALEB MEISTER
Smoke Detectors 1/26/2023 Approved CALEB MEISTER