327-327 1/2 N CHICAGO ST 90033

Certificate Information: 327-327 1/2 N CHICAGO ST 90033

Application / Permit
21010-10000-05633
Plan Check / Job No.
B21LA20241
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 4 STORY DUPLEX WITH RECREATION ROOM AND GARAGE (FRONT)
Permit Issued
Issued on 8/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 STARR CHEN
Corrections Issued 11/22/2021 STARR CHEN
Building Plans Picked Up 12/2/2021 APPLICANT
Quality Review Completed 7/15/2022 ALLEN MANALANSAN
Plan Check Approved 7/28/2022 STARR CHEN
Issued 8/26/2022 APPLICANT
CofO in Progress 10/24/2024 OSVALDO PARAMO
Permit Finaled 11/1/2024 DEROLD HAUFF
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/7/2021 KHOUNG LE
Permit Cleared 12/7/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 12/10/2021 KHOUNG LE
Sewer availability Cleared 12/10/2021 KHOUNG LE
Tenant Habitability Plan Cleared 12/13/2021 RICHARD BRINSON
Building over 36-ft Cleared 12/22/2021 CALOSHA APPROVED
Clean Up Green Up Cleared 12/28/2021 MAXFIELD VERMY
Low Impact Development Cleared 12/28/2021 KHAING AYE
Roof/Waste drainage to street Cleared 12/29/2021 THAN WIN
Trees in Parkway Cleared 12/29/2021 ADALBERTO VERA
Frnt yard landscape/Water mgmt Cleared 1/11/2022 MAXFIELD VERMY
Hydrant and Access approval Cleared 3/5/2022 GILBERT URREA
Work Adjacent to Public Way Cleared 3/24/2022 ARMEN SARKISIAN
GPI Written Notices Cleared 5/31/2022 STARR CHEN
Grading Pre-Inspection Cleared 5/31/2022 STARR CHEN

Contact Information

Architect Chan,, Philip K; Lic. No.: C38915 711 S FIRST AVE      ARCADIA, CA 91006
Contractor Sunny Construction & Development Corporation; Lic. No.: 737977-B 711 S FIRST AVE      ARCADIA, CA 91006
Engineer Jones,, Ryan Keith; Lic. No.: GE2852 1253 W MASLINE ST      COVINA, CA 91722
Engineer Jong,, Hank Hsing-Lian; Lic. No.: C45846 11819 GOLDRING ROAD UNIT A      ARCADIA, CA 91006
Engineer Lin,, Jason; Lic. No.: S6095 801 CREST VISTA DR      MONTEREY PARK, CA 91754
Landscape Architect Garcia,, Manuel R.; Lic. No.: LA3929 228 E CAMDEN ST      GLENDORA, CA 91740

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 12/15/2022 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 12/15/2022 Approved OSVALDO PARAMO
Underground Mechanical 12/15/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/20/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 12/21/2022 Conditional Approval OSVALDO PARAMO
Reinforced Masonry Frame 12/30/2022 Partial Approval RUBEN SALAS
Reinforced Masonry Frame 1/26/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 1/27/2023 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/3/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 2/6/2023 Conditional Approval OSVALDO PARAMO
PLUMBING-Rough 2/7/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 2/15/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 2/15/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 2/17/2023 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 2/22/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 3/9/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 3/21/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/21/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 4/11/2023 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 7/7/2023 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/7/2023 Corrections Issued OSVALDO PARAMO
Shower Pan 7/7/2023 Approved OSVALDO PARAMO
HVAC-Rough 7/11/2023 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 7/12/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 7/12/2023 Approved OSVALDO PARAMO
HVAC-Rough 7/18/2023 Approved OSVALDO PARAMO
Deputy Wood Construction 8/1/2023 Approved DONALD CRICHLOW
BUILDING-Rough-Frame 8/3/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 8/3/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 8/3/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Partial Approval ALIZAH MAYAGOITIA
Insulation 8/11/2023 Partial Approval ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 8/11/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/18/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Approved OSVALDO PARAMO
Green Building Rough 8/18/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/11/2023 Partial Approval OSVALDO PARAMO
Insulation 9/12/2023 Approved OSVALDO PARAMO
Drywall Nailing 9/20/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 9/29/2023 Approved AMY COLIN
Sewer 12/7/2023 Partial Approval AMY COLIN
Underground Mechanical 1/31/2024 Partial Approval OSVALDO PARAMO
Underground Mechanical 3/20/2024 Partial Approval OSVALDO PARAMO
Underground Mechanical 3/26/2024 Approved OSVALDO PARAMO
Underground Mechanical 5/13/2024 Partial Inspection OSVALDO PARAMO
PLUMBING-Final 7/24/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 8/27/2024 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 8/30/2024 Approved OSVALDO PARAMO
PLUMBING-Final 9/3/2024 Approved OSVALDO PARAMO
HVAC-Final 9/13/2024 Approved OSVALDO PARAMO
Gas Test 9/23/2024 Not Ready for Inspection LUIS CASTRO
Gas Test 9/30/2024 Approved OSVALDO PARAMO
Final 10/16/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 10/16/2024 Approved OSVALDO PARAMO
Green Building Final 10/16/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 10/16/2024 Approved OSVALDO PARAMO
Smoke Detectors 10/16/2024 Approved OSVALDO PARAMO
Structural Steel Frame 10/16/2024 Approved OSVALDO PARAMO
Final 10/23/2024 OK to Issue CofO OSVALDO PARAMO